Latest Update

Construction Equipment Coming Soon

Sep 13, 2019
VIL will be bringing equipment to the site Monday, delivering materials Tuesday, and beginning clearing along the creek Wednesday.  The Creek stabilization work will take about 3 weeks, then they will do the storm sewer work in Buckingham Ct beginning the week of Oct 7 and lasting about 1 week