Latest Update
Construction Update
The 2020 Concrete Road Program project is nearly completed! The last of the concrete will be poured today. The driveways shown below will be open by Monday, October 12.
Avon Ravines #2
October 5 - Concrete placement on driveway approaches (Woodridge Ct)
Stratford Knolls
October 5 - Concrete placement on driveway approaches (Chalet Dr)
The construction crew has started removing traffic control devices, clean out bags, and other miscellaneous items. The crew will remain on site performing restoration, joint sealing, clean up, and other punch list items, including mailbox repairs, cracked concrete repairs, etc.
On behalf of the construction team, we want to thank everyone for their cooperation and patience during this project.
Construction Updates
Construction Update
The 2020 Concrete Road Program project is nearly completed! The last of the concrete will be poured today. The driveways shown below will be open by Monday, October 12.
Avon Ravines #2
October 5 - Concrete placement on driveway approaches (Woodridge Ct)
Stratford Knolls
October 5 - Concrete placement on driveway approaches (Chalet Dr)
The construction crew has started removing traffic control devices, clean out bags, and other miscellaneous items. The crew will remain on site performing restoration, joint sealing, clean up, and other punch list items, including mailbox repairs, cracked concrete repairs, etc.
On behalf of the construction team, we want to thank everyone for their cooperation and patience during this project.
Construction Update
Construction continues in the following subdivisions:
• Wildflower (Primrose Dr)
• Covington Place (Brunswick, Waverly Dr)
• Cumberland Hills (Poco Ct)
• Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
• Meadowbrook Valley (Box Canyon Ct)
• Stratford Knolls (Canterbury Trail Dr, Chalet Dr)
Primrose Drive (Two-way traffic will be maintained)
September 16 - Concrete curing at Primrose and Goldenrod intersection and crossover between the islands
Covington Place
September 10 to September 17 - Concrete cure time
Poco Court
September 11 to September 17 - Concrete cure time
Avon Ravines #2
September 9 to September 16 - Concrete cure time
Box Canyon Court
September 14 - Concrete removal on northbound lane
September 14 to September 15 - Stone placement, concrete forming, and edge drain installation
September 16 to September 18 - Concrete placement
September 18 to September 25 - Concrete cure time
Stratford Knolls (One-way traffic will be maintained north and east on Chalet Dr and on southbound Canterbury Trail Dr during Phase 2; see traffic plan)
September 16 - Concrete placement on driveway approaches (phase 2)
September 15 to September 18 - Concrete removal (phase 3)
September 18 to September 21 - Stone placement, concrete forming, and edge drain installation
September 22 to September 25 - Concrete placement
Construction Update
NOTE: Due to the rain over the holiday weekend, construction work has been slightly delayed.
Construction continues in the following subdivisions:
• Wildflower (Primrose Dr)
• Covington Place (Brunswick, Waverly Dr)
• Cumberland Hills (Poco Ct)
• Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
• Meadowbrook Valley (Box Canyon Ct)
• Stratford Knolls (Canterbury Trail Dr, Chalet Dr)
Primrose Drive (Two-way traffic will be maintained)
September 9 - Concrete placement at the Primrose and Goldenrod intersection and crossover between the islands
September 9 to September 16 - Concrete cure time
Covington Place
September 10 - Concrete placement on westbound Brunswick
September 10 to September 17 - Concrete cure time
Poco Court
September 11 - Concrete placement on the westbound side
September 11 to September 18 - Concrete cure time
Avon Ravines #2
September 9 - Concrete placement on Woodridge Ct
September 9 to September 16 - Concrete cure time
Box Canyon Court
September 10 to September 11 - Concrete removal on north bound lane
Stratford Knolls (One-way traffic will be maintained north and east on Chalet Dr and on southbound Canterbury Trail Dr during Phase 2; see traffic plan)
September 3 to September 10 - Concrete cure time (phase 2)
September 14 to September 17 - Concrete removal (phase 3)
Construction Update
NOTE: Due to the heavy rain last week, construction work has been slightly delayed.
Construction continues in the following subdivisions:
Wildflower (Primrose Dr)
Covington Place (Brunswick, Waverly Dr)
Cumberland Hills (Poco Ct)
Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
Meadowbrook Valley (Box Canyon Ct)
Stratford Knolls (Canterbury Trail Dr, Chalet Dr)
Primrose Drive(Two-way traffic will be maintained)
August 31 to September 2 - Concrete cure time
September 2 - Concrete removal at Primrose and Goldenrod intersection
Covington Place
September 2 - Concrete removal on westbound Brunswick
September 3 - Base preparation, edge drain, concrete form placement
September 10 - Concrete placement on westbound Brunswick
Poco Court
September 3 to September 4 - Concrete removal on the westbound side
September 4 to September 5 - Base preparation, edge drain, concrete form placement
Avon Ravines #2
August 31 to September 1 - Concrete removal (phase 3)
September 1 to September 2 - Base preparation, edge drain, concrete form placement
September 2 - Concrete placement on driveway approaches
September 8 to September 9 - Concrete placement (phase 3)
Box Canyon Court
August 31 to September 1 - Concrete placement on southbound side
September 1 to September 8 - Concrete cure time
Stratford Knolls (One-way traffic will be maintained north and east on Chalet Dr and on southbound Canterbury Trail Dr during Phase 2; see traffic plan)
August 31 - Base preparation, edge drain, concrete form placement
September 1 to September 4 - Concrete placement (phase 3)
September 4 to September 11 - Concrete cure time (phase 3
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Begins Today
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.
CLARK FRENCH - PROJECT MANAGER
SPALDING DEDECKER
(248) 844-6286
CFRENCH@SDA-ENG.COM