Latest Update
Construction Update
Nov 02, 2021
Restoration is in progress. Although topsoil and seeding has been completed for the majority of the streets, it has not been accepted. We understand much grass growth still needs to be established. We are diligently working with the contractor to much improve the lawn restoration during this fall growing season. Ongoing maintenance is being performed for topsoil and seed that is washed away due to heavy down pours. Please see an updated construction schedule below.
Meadowbrook Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Munster Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Campus Ct
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Campus Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Sumac Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Aynsley Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Wedgewood/Arbor Creek Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Old Homestead Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Summit Ct
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Summit Ridge
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Cobridge Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Read More
Meadowbrook Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Munster Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Campus Ct
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Campus Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Sumac Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Aynsley Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Wedgewood/Arbor Creek Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Old Homestead Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Summit Ct
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Summit Ridge
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Cobridge Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Construction Updates
Construction Update
on Nov 02, 2021
+
Restoration is in progress. Although topsoil and seeding has been completed for the majority of the streets, it has not been accepted. We understand much grass growth still needs to be established. We are diligently working with the contractor to much improve the lawn restoration during this fall growing season. Ongoing maintenance is being performed for topsoil and seed that is washed away due to heavy down pours. Please see an updated construction schedule below.
Meadowbrook Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Munster Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Campus Ct
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Campus Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Sumac Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Aynsley Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Wedgewood/Arbor Creek Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Old Homestead Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Summit Ct
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Summit Ridge
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Cobridge Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Meadowbrook Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Munster Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Campus Ct
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Campus Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Sumac Rd
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Aynsley Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Wedgewood/Arbor Creek Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Old Homestead Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Summit Ct
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Summit Ridge
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Cobridge Dr
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Construction Update
on Oct 18, 2021
+
October 18-22
Restoration is in progress. All lanes and driveways are open on all roads listed below. Additionally, backfill, topsoil, seeding, and joint sealing has been completed; waiting for the grass to establish.
Meadowbrook Dr
Munster Rd
Campus Ct
Campus Rd
Sumac Rd
Aynsley Dr
Wedgewood/Arbor Creek Dr
Old Homestead Dr
Summit Ct
Summit Ridge
Cobridge Dr
We would like to thank all the residents for their patience and understanding throughout this construction season. We appreciate all your feedback!
Check out the 2021 Rochester Hills Local Road Program Overview Video and the Road Program #1 Photo Slideshow below!
Construction Update
on Sep 28, 2021
+
Restoration is in progress. Although topsoil and seeding have been completed at most locations, grass still needs to establish. SD is working diligently with the contractor to improve lawn restoration. Ongoing maintenance is being performed for topsoil and seed that has been washed away due to heavy rain. Please see an updated construction schedule below.
Meadowbrook Dr
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Munster Rd
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Campus Ct
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Campus Rd
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Sumac Rd
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Aynsley Dr
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Wedgewood/Arbor Creek Dr
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, and joint sealing completed. Seeding is scheduled to be completed this week, weather dependent.
Old Homestead Dr
September 27-October 1 – All lanes/drives open. Backfill and topsoil are complete. Seeding is scheduled to be completed this week, weather dependent. Joint is sealing is to be determined.
Summit Ct
September 27-October 1 – All lanes and driveways open. Backfill and joint sealing completed. Topsoil and seeding are scheduled to be completed this week, weather dependent.
Summit Ridge
September 27-October 1 – All lanes and driveways open. Backfill and joint sealing completed. Topsoil and seeding are scheduled to be completed this week, weather dependent.
Cobridge Dr
September 27-October 1 – All lanes and driveways open. Backfill and joint sealing completed. Topsoil and seeding are scheduled to be completed this week, weather dependent.
Construction Update
on Sep 20, 2021
+
Restoration is in progress. Although topsoil and seeding have been completed at most locations, grass still needs to establish. SD is working diligently with the contractor to improve lawn restoration. Please complete irrigation repairs ASAP, if applicable. Please see an updated construction schedule below.
Meadowbrook Dr
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Munster Rd
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Campus Ct
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Campus Rd
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Sumac Rd
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Aynsley Dr
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Wedgewood/Arbor Creek Dr
September 20-24 – All lanes and driveways open. Backfill and joint sealing completed. Topsoil and seeding are scheduled to be completed this week, weather dependent.
Old Homestead Dr
September 20-24 – All lanes/drives open. Backfill is complete. Topsoil and seeding are scheduled to be completed this week, weather dependent. Joint sealing could not be completed last week, as portions of the street were covered with building materials for homeowner improvements. Joint is sealing is to be determined.
Summit Ct
September 20-24 – All lanes and driveways open. Backfill and joint sealing completed. Topsoil and seeding are scheduled to be completed this week, weather dependent.
Summit Ridge
September 20-24 – All lanes and driveways open. Backfill and joint sealing completed. Topsoil and seeding are scheduled to be completed this week, weather dependent.
Cobridge Dr
September 20-24 – All lanes and driveways open. Backfill and joint sealing completed. Topsoil and seeding are scheduled to be completed this week, weather dependent.
Construction Update
on Sep 13, 2021
+
Restoration is in progress. Although topsoil and seeding have been completed at most locations, grass still needs to establish. SD is working diligently with the contractor to improve lawn restoration. Please complete irrigation repairs ASAP, if applicable. Please see an updated construction schedule below.
Meadowbrook Dr
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Munster Rd
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Campus Ct
September 13 - 17 – Al lanes and driveways open. Backfill, topsoil, and seeding completed; waiting for the grass to establish. Joint sealing was rescheduled by the contractor.
Campus Rd
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, and seeding completed; waiting for the grass to establish. Joint sealing was rescheduled by the contractor.
Sumac Rd
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Aynsley Dr
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Wedgewood/Arbor Creek Dr
September 13 - 17 – All lanes and driveways are anticipated to be open Monday. Sawcutting and sealing are anticipated next week. Restoration to be determined.
Old Homestead Dr
September 13 - 17 – All lanes open. Concrete cure time. Sawcutting and sealing are anticipated next week. Restoration to be determined.
Summit Ct
September 7 - 10 – All lanes open. Concrete cure time. Sawcutting and sealing are anticipated next week. Restoration to be determined.
Summit Ridge
September 13 - 17 – All lanes open. Sawcutting and sealing are anticipated next week. Restoration to be determined.
Cobridge Dr
September 13 - 17 – All lanes open. Concrete cure time. Sawcutting and sealing are anticipated next week. Restoration to be determined.
Construction Update
on Sep 07, 2021
+
Restoration is in progress at some locations. Please see an updated construction schedule below.
Meadowbrook Dr
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Munster Rd
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Campus Ct
September 7 - 10 – Al lanes and driveways open. Backfill, topsoil, and seeding completed; waiting for the grass to establish. Joint sealing was rescheduled by the contractor.
Campus Rd
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, and seeding completed; waiting for the grass to establish. Joint sealing was rescheduled by the contractor.
Sumac Rd
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Aynsley Dr
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Wedgewood/Arbor Creek Dr
(Two-way traffic will be maintained through the intersection)
September 7 - 10 – Concrete placement on the northwest and southeast quadrants. All other lanes are open.
Old Homestead Dr
September 7 - 10 – Complete concrete placement on southbound lane driveways; concrete cure time. Once the concrete has cured, all lanes and driveways will be open. Restoration and joint sealing to be determined.
Summit Ct
September 7 - 10 – All lanes open on Tuesday. Complete concrete placement on driveways; concrete cure time. Once the concrete has cured, all lanes and driveways will be open. Restoration and joint sealing to be determined.
Summit Ridge
September 7 - 10 – Northbound lane open on Tuesday. Patch replacement on southbound lane. Restoration and joint sealing to be determined.
Cobridge Dr
(Two-way northbound traffic will be maintained)
September 7 - 10 – Concrete cure time on southbound lane. Concrete placement on driveways. Restoration and joint sealing to be determined.
Construction Update
on Aug 27, 2021
+
Restoration is in progress at some locations. Please complete irrigation repairs ASAP, if applicable. Please see an updated construction schedule below.
Meadowbrook Dr
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Munster Rd
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Campus Ct
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, and seeding completed; waiting for the grass to establish. Joint sealing was delayed last week and is scheduled for this week.
Campus Rd
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, and seeding completed; waiting for the grass to establish. Joint sealing was delayed last week and is scheduled for this week.
Sumac Rd
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Aynsley Dr
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Wedgewood/Arbor Creek Dr
(Two-way traffic will be maintained through the intersection)
August 30-September 3 – Concrete cure time for the northeast quadrant. Once the concrete has cured, begin demolition, base preparation, edge drain installation, concrete forms, and concrete placement for northwest and southeast quadrants.
Old Homestead Dr
(One-way northbound traffic will be maintained)
August 30-September 3 – Complete concrete placement for southbound lane; concrete cure time. Once the concrete has cured, complete construction for driveways on southbound lane.
Summit Ct
August 30-September 3 – Finish base preparation, concrete forms, and placement of concrete for northbound Summit Ridge and for westbound Summit Ct.
Cobridge Dr
(Two-way northbound traffic will be maintained)
August 30-September 3 – Demolition, base preparation, edge drain installation, concrete forms, and concrete placement on southbound lane begins on Monday, August 30.
Construction Update
on Aug 23, 2021
+
Restoration is in progress for most locations. Please begin irrigation repairs ASAP, if applicable. Please see an updated construction schedule below.
Meadowbrook Dr
August 23-27 – All lanes and driveways open. Backfill, topsoil, and seeding completed; joint sealing is scheduled this week.
Munster Rd
August 23-27 – All lanes and driveways open. Backfill, topsoil, and seeding completed; joint sealing is scheduled this week.
Campus Ct
August 23-27 – All lanes and driveways open. Backfill, topsoil, and seeding completed; joint sealing is scheduled this week.
Campus Rd
August 23-27 – All lanes and driveways open. Backfill, topsoil, and seeding completed; joint sealing is scheduled this week.
Sumac Rd
August 23-27 – All lanes and driveways open. Backfill, topsoil, and seeding completed; joint sealing is scheduled this week.
Aynsley Dr
August 23-27 – All lanes and driveways open. Backfill, topsoil, and seeding completed; joint sealing is scheduled this week.
Wedgewood/Arbor Creek Dr
(Two-way traffic will be maintained through the intersection)
August 23-27 – Concrete placement on the northeast corner of the intersection; concrete cure time.
Old Homestead Dr
(One-way northbound traffic will be maintained)
August 23-27 – Begin demolition, base preparation, edge drain installation, and concrete forms on the southbound lane.
Summit Ct
August 23-27 – Base preparation, concrete forms, and concrete placement on southbound Summit Ridge. Concrete cure time.
Cobridge Dr
(Two-way southbound traffic will be maintained)
August 23-27 – Paving on northbound lane; concrete cure time.
Construction Update
on Aug 16, 2021
+
Attention Residents:
Due to inclement weather, there has been a power outage at the concrete plant. Concrete placement scheduled this week has been delayed due to this. We appreciate your patience and cooperation during this construction phase. Please see an updated construction schedule below.
Meadowbrook Dr
August 16-20 – All lanes and driveways open. Backfill and topsoil behind the back of curb has been completed; joint sealing is tentatively set for August 17.
Munster Rd
August 16-20 – All lanes and driveways open. Backfill and topsoil behind the back of curb has been completed; joint sealing is tentatively set for August 17.
Campus Ct
August 16-20 – All lanes and driveways open. Backfill and topsoil behind the back of curb has been completed; joint sealing to be determined.
Campus Rd
August 16-20 – All lanes and driveways open. Backfill and topsoil behind the back of curb has been completed; joint sealing is tentatively set for August 17.
Sumac Rd
August 16-20 – All lanes and driveways open. Backfill and topsoil behind the back of curb has been completed; joint sealing is tentatively set for August 17.
Aynsley Dr
August 16-20 – All lanes and driveways open. Backfill and topsoil behind the back of curb has been completed; joint sealing is tentatively set for August 17.
Wedgewood/Arbor Creek Dr
(Two-way traffic will be maintained through the intersection)
August 16-20 – Demolition, base preparation, edge drain installation, concrete forms for the northeast corner of the intersection; concrete cure time. Waiting for concrete.
Old Homestead Dr
(One-way southbound traffic will be maintained)
August 16-20 – Waiting for concrete to finish concrete placement for the northbound lane.
Summit Ct
August 16-20 – Continued base preparation, edge drain installation, and concrete forms for the northeastbound lane. Waiting for concrete.
Cobridge Dr
(Two-way southbound traffic will be maintained)
August 16-20 – Begin demolition, base preparation, edge drain installation, and concrete forms for the northbound lane. Waiting for concrete.
Backfill behind back of curb for completed roads is in progress. Please begin irrigation repairs ASAP. Topsoil and seeding with mulch to follow.
Construction Update
on Aug 09, 2021
+
Attention Residents:
Backfill behind back of curb for completed roads is expected to begin very soon. Please begin irrigation repairs ASAP. Topsoil and seeding with mulch to follow. We appreciate your patience and cooperation during this construction phase. Please see an updated construction schedule below.
Meadowbrook Dr
August 9-13 – All lanes and driveways open. Backfill and topsoil behind the back of curb has been completed; joint sealing to be determined.
Munster Rd
August 9-13 – All lanes and driveways open. Backfill and topsoil behind the back of curb has been completed; joint sealing to be determined.
Campus Ct
August 9-13 – All lanes and driveways open. Backfill and topsoil behind the back of curb has been completed; joint sealing to be determined.
Campus Rd
August 9-13 – All lanes and driveways open. Finishing backfill and topsoil behind the back of curb has been completed; joint sealing to be determined.
Sumac Rd
August 9-13 – All lanes and driveways open. Finishing backfill and topsoil behind the back of curb has been completed; joint sealing to be determined.
Aynsley Dr
(Two-way westbound traffic will be maintained)
August 9-13 – Concrete cure time on eastbound lane and driveways. Open to traffic by Friday (anticipated).
Wedgewood/Arbor Creek Dr
(Two-way traffic will be maintained through the intersection)
August 9-13 – Concrete placement for the southwest corner of the intersection; concrete cure time.
Old Homestead Dr
(One-way southbound traffic will be maintained)
August 9-13 – Continue base preparation, edge drain installation, concrete forms, and concrete placement for the northbound lane.
Summit Ct
(One-way southbound traffic will be maintained)
August 9-13 – Continued base preparation, edge drain installation, concrete forms, for the northeastbound lane.
Cobridge Dr
(Two-way southbound traffic will be maintained)
August 16 – Begin demolition, base preparation, edge drain installation, concrete forms, and concrete placement for the northbound lane.
Construction Update
on Aug 02, 2021
+
Attention Residents:
Backfill behind back of curb for completed roads is expected to begin very soon. Please begin irrigation repairs ASAP. Topsoil and seeding with mulch to follow. We appreciate your patience and cooperation during this construction phase. Please see an updated construction schedule below.
Meadowbrook Dr
August 2-6 – All lanes and driveways open. Restoration and joint sealing to be determined.
Munster Rd
August 2-6 – All lanes and driveways open. Backfill and topsoil has been completed behind the back of curb. Joint sealing to be determined.
Campus Ct
August 2-6 – All lanes and driveways open. Finish backfill and topsoil behind the back of curb. Joint sealing to be determined.
Campus Rd
(Two-way traffic will be maintained in westbound lane)
August 2-6 – Concrete cure time for eastbound lane driveways. Restoration and joint sealing to be determined.
Sumac Rd
(Both lanes open to traffic)
August 2-6 – Concrete cure time for eastbound lane patch. Concrete placement on westbound lane. Restoration and joint sealing to be determined.
Aynsley Dr>
(Two-way westbound traffic will be maintained)
August 2-6 – Finish demolition, base preparation, edge drain installation, concrete forms, and concrete placement for the eastbound lane.
Wedgewood/Arbor Creek Dr
(Two-way traffic will be maintained through the intersection)
August 2-6 – Begin demolition, base preparation, edge drain installation, concrete forms, and concrete placement for the southwest corner of the intersection.
Old Homestead Dr
(One-way southbound traffic will be maintained)
August 3-6 – Begin demolition, base preparation, edge drain installation, concrete forms, and concrete placement for the northbound lane.
Summit Ct
(One-way southbound traffic will be maintained)
August 6 – Begin demolition on the cul-de-sac and northbound lane. Southbound lane to remain until cul-de-sac and northbound lane are complete (Anticipated).
Construction Update
on Jul 26, 2021
+
Due to inclement weather, construction has been slightly delayed. Please see an updated construction schedule below.
Meadowbrook Dr
(Both lanes are open to traffic)
July 26-30 – Cure time for replaced concrete. Diligently assisting contractor to provide asphalt drive repairs ASAP.
Munster Rd
Eyebrow open to traffic. Backfill and topsoil has been completed behind the back of curb. Joint sealing to be determined.
Campus Ct
(Both lanes open to traffic)
July 26-30 – Concrete placement on two remaining driveways. Backfill and topsoil has been completed behind the back of curb.
Campus Rd
(Two-way traffic will be maintained in westbound lane)
July 26-30 – Complete demolition, base preparation, edge drain installation, concrete forms and concrete placement on the eastbound lane.
Sumac Rd
(Both lanes open to traffic)
July 26-30 – Concrete placement on damaged areas and remaining driveways.
Aynsley Dr
(Two-way eastbound traffic will be maintained)
July 26-30 – Concrete cure time placement on the westbound lane. Demolition, base preparation, edge drain installation, and concrete forms of the eastbound lane begins.
Construction Update
on Jul 19, 2021
+
Due to inclement weather, construction has been slightly delayed. Please see an updated construction schedule below.
Meadowbrook Dr
(Both lanes are open to traffic)
July 19-23 – Remove and replace poorly manufactured concrete. The schedule for repair and driveway work is yet to be determined by the contractor.
Munster Rd
Eyebrow open to traffic. Restoration and sealing date to be determined.
Campus Ct
(Both lanes open to traffic)
July 19-23 – Concrete placement on driveways.
Campus Rd
(Two-way traffic will be maintained in eastbound lane)
July 19-23 – Complete intersection of Campus Rd and Campus Ct.
Sumac Rd
(Both lanes open to traffic)
July 19-23 – Concrete placement on driveways. Westbound lane open to traffic.
Aynsley Dr
(Two-way eastbound traffic will be maintained)
July 19-23 – Concrete placement on the westbound lane.
Construction Update
on Jul 12, 2021
+
Due to inclement weather, construction has been slightly delayed. Please see an updated construction schedule below.
Meadowbrook Dr
Both lanes are open to traffic; however, due to poorly manufactured concrete, a short portion of the road will need to be removed and replaced. The schedule for repair and driveway work is yet to be determined by the contractor.
Munster Rd
Eyebrow open to traffic. Restoration and sealing date to be determined.
Campus Ct
(Two-way traffic will be maintained in westbound and southbound lanes)
July 12-16 – Concrete placement on northbound and eastbound lanes.
Campus Rd
(Two-way traffic will be maintained in eastbound lane)
July 12-16 – Concrete forms and concrete placement on westbound lane.
Sumac Rd
(One-way eastbound traffic will be maintained; Cypress intersection is open)
July 12-16 – Concrete placement on driveways. Westbound lane open to traffic.
Aynsley Dr
(Two-way eastbound traffic will be maintained)
July 12-16 – Demolition, base preparation, edge drain installation, concrete forms, and concrete placement on the westbound lane begins (Anticipated).
Construction Update
on Jul 02, 2021
+
Due to inclement weather and Independence Day holiday, construction has slightly delayed. Please see an updated construction schedule below.
Meadowbrook Dr
Both lanes are open to traffic; however, due to poorly manufactured concrete, a short portion of the road will need to be removed and replaced. The schedule for repair and driveway work is yet to be determined by the contractor.
Munster Rd
Eyebrow open to traffic. Restoration and sealing date to be determined.
Campus Ct
(Two-way traffic will be maintained in westbound and southbound lanes)
July 6-9 – Concrete placement on northbound and eastbound lanes.
Campus Rd
(Two-way traffic will be maintained in eastbound lane)
July 6-9 – Demolition, base preparation, edge drain, concrete forms and concrete placement on westbound lane.
Sumac Rd
(One-way eastbound traffic will be maintained; Cypress intersection is open)
July 6-9 – Concrete placement on westbound lane.
Aynsley Dr
(Two-way eastbound traffic will be maintained)
July 6-9 – Demolition, base preparation, edge drain installation, concrete forms, and concrete placement on the westbound lane begins (Anticipated).
NOTE TO RESIDENTS
Please keep vehicles away from mailboxes and/or out of the mail delivery trucks' path. We appreciate your cooperation during this construction phase.
Construction Update
on Jun 28, 2021
+
Inclement weather has delayed concrete placement and demolition for all locations. All planned work is weather dependent. Please see an updated schedule of construction.
Meadowbrook Dr
(One-way eastbound traffic will be maintained)
June 28-July 2 – Concrete cure time
Munster Rd
Eyebrow open to traffic. Restoration and sealing date to be determined.
Campus Rd/Ct
(Two-way traffic will be maintained)
June 28-July 2 – Westbound and southbound lanes will be opened. Demolition, base preparation, edge drain installation, concrete forms and concrete placement on northbound and eastbound lanes.
Sumac Rd
(One-way eastbound traffic will be maintained; Cypress intersection is open)
June 28-July 2 – Base preparation, edge drain, concrete form, and concrete placement on westbound lane.
Aynsley Dr
(Two-way eastbound traffic will be maintained)
July 2 – Demolition, base preparation, edge drain installation, concrete forms, and concrete placement on the westbound lane begins (Anticipated).
NOTE TO RESIDENTS
Please keep vehicles away from mailboxes and/or out of the mail delivery trucks' path. We appreciate your cooperation during this construction phase.
Construction Update
on Jun 21, 2021
+
Please see an updated schedule of construction. Your patience and understanding during this construction project is very much appreciated.
Meadowbrook Dr
(One-way eastbound traffic will be maintained)
June 21-25 – Concrete placement on westbound lane (Anticipated).
Munster Rd
Eyebrow open to traffic. Restoration and sealing date to be determined.
Campus Rd/Ct
(Two-way traffic will be maintained)
June 21-25 – Concrete cure time.
Sumac Rd
(One-way eastbound traffic will be maintained; Cypress intersection is open)
June 21-25 – Demolition, base preparation, edge drain, concrete form, and concrete placement on westbound lane.
NOTE TO RESIDENTS
Please keep vehicles away from mailboxes and/or out of the mail delivery trucks' path. We appreciate your cooperation during this construction phase.
Construction Update
on Jun 14, 2021
+
Please see an updated schedule of construction. Your patience and understanding during this construction project is very much appreciated.
Meadowbrook Dr
(One-way eastbound traffic will be maintained)
June 14-18 – Demolition, base preparation, edge drain installation, concrete forms and concrete placement on westbound lane continues.
Munster Rd
Eyebrow open to traffic. Restoration and sealing date to be determined.
Campus Rd/Ct
(Two-way traffic will be maintained)
June 14-15 – Concrete placement on westbound and southbound lane.
Sumac Rd
(One-way westbound traffic will be maintained until eastbound can be opened)
June 17 – Anticipated date for demolition, base preparation, edge drain, concrete form, and concrete placement on westbound lane.
NOTE TO RESIDENTS
Please keep vehicles away from mailboxes and/or out of the mail delivery trucks' path. We appreciate your cooperation during this construction phase.
Construction Update
on Jun 07, 2021
+
Please see an updated schedule of construction. Your patience and understanding during this construction project is very much appreciated.
Meadowbrook Dr
(One-way westbound traffic will be maintained)
June 11 – Demolition on westbound lane begins (Anticipated).
Munster Rd
Eyebrow open to traffic. Restoration and sealing date to be determined.
Campus Rd/Ct
(Two-way traffic will be maintained)
June 7-11 – Demolition, base preparation, edge drain, concrete form, and concrete placement on southbound lane.
Sumac Rd
(One-way westbound traffic will be maintained)
June 7-11 – Demolition, base preparation, edge drain, concrete form, and concrete placement on eastbound lane.
Construction Update
on May 28, 2021
+
Construction will resume after Memorial Day holiday. Please see an updated schedule of construction. Your patience and understanding during this construction project is very much appreciated.
Meadowbrook Dr
(One-way westbound traffic will be maintained)
June 1-4 – Concrete placement on eastbound lane; concrete cure time
June 7 – Demolition on westbound lane begins (Anticipated)
Munster Rd
(Two-way traffic will be maintained; eyebrow closed)
June 1-4 – Concrete cure time; restoration begins
Campus Rd/Ct
(Two-way traffic will be maintained)
June 1-4 – Concrete placement in eyebrow. Demolition, base preparation, edge drain, concrete form placement in the cul-de-sac.
Sumac Rd
(One-way westbound traffic will be maintained)
June 1-4 – Concrete placement on southbound Lake Forest Rd, and southwest corner of Sumac and Cypress. Demolition on eastbound Sumac begins.
Construction Update
on May 24, 2021
+
Please see an updated schedule of construction. Your patience and understanding during this construction project is very much appreciated.
Meadowbrook Dr
(One-way westbound traffic will be maintained)
May 25 – Storm sewer crossing to be complete at Meadowbrook and Adams Road. Intersection will be closed for westbound traffic. A flagger will be provided to maintain two way traffic on Meadowbrook Rd.
May 26 – Concrete pouring on eastbound lane
Munster Rd
(Two-way traffic will be maintained; eyebrow closed)
May 24-28 – Concrete pouring continues
Campus Rd/Ct
(Two-way traffic will be maintained)
May 24-28 – Concrete pouring in cul-de-sac and eyebrow. Demolition, base preparation, edge drain, concrete form placement on eastbound Campus Rd.
Sumac Rd
(One-way westbound traffic will be maintained)
May 27– Demolition, base preparation, edge drain, concrete form placement on eastbound Sumac Rd begins (Lake Forest Rd to Tanglewood Dr).
Construction Update
on May 17, 2021
+
Please see an updated schedule of construction. Your patience and understanding during this construction project is very much appreciated.
Meadowbrook Dr
(One-way traffic will be maintained)
May 17-21 – Demolition, base preparation, edge drain, concrete form placement continues
Munster Rd
(Two-way traffic will be maintained; eyebrow closed)
May 17-21 – Demolition, base preparation, edge drain, concrete form placement continues
Campus Rd
(Two-way traffic will be maintained)
May 17-21 – Demolition, base preparation, edge drain, concrete form placement in the cul-de-sac and eyebrow.
Construction Update 1
on May 10, 2021
+
Rochester Hills 2021 Concrete Road Program #1 construction is anticipated to begin on the week of May 10 in the following areas: Meadowbrook Dr., Meadowbrook Valley No. 2. Below is tentative schedule of construction. Please note that these dates are subject to change. Your patience and understanding during this construction project is very much appreciated.
Meadowbrook Dr
(One-way traffic will be maintained)
May 10 – Demolition, base preparation, edge drain, concrete form placement begins
Munster Rd eyebrow
May 14 – Demolition begins (anticipated)
Construction starting in April
on Apr 09, 2021
+
More construction details will be coming soon. Stay turned.
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.
Grady Rollins - Project Manager
Spalding DeDecker
(248) 844-5400
grollins@sda-eng.com