Latest Update
Construction Update
Restoration is in progress. Although topsoil and seeding have been completed for the majority of the streets, it has not been accepted. We understand much grass growth still needs to be established. We are diligently working with the contractor to much improve the lawn restoration during this fall growing season. Ongoing maintenance is being performed for topsoil and seed that is washed away due to heavy downpours. Please see an updated construction schedule below.
Snowden Court
November 1-5 – All lanes and driveways open. Saw cutting, joint sealing, backfill, topsoil, and seeding TBD but expected in the next two weeks or sooner.
WEATHER LIMITATIONS! Inclement weather may delay concrete placement. All planned work is weather dependent.
Arlington Drive
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Hidden Lane
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Crestline Lane
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Daylily Drive
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Lexington Drive/Ternbury Drive
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Thornridge Court
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Slade Court
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Kirkton Court
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Brittany Court
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Construction Updates
Construction Update
Restoration is in progress. Although topsoil and seeding have been completed for the majority of the streets, it has not been accepted. We understand much grass growth still needs to be established. We are diligently working with the contractor to much improve the lawn restoration during this fall growing season. Ongoing maintenance is being performed for topsoil and seed that is washed away due to heavy downpours. Please see an updated construction schedule below.
Snowden Court
November 1-5 – All lanes and driveways open. Saw cutting, joint sealing, backfill, topsoil, and seeding TBD but expected in the next two weeks or sooner.
WEATHER LIMITATIONS! Inclement weather may delay concrete placement. All planned work is weather dependent.
Arlington Drive
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Hidden Lane
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Crestline Lane
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Daylily Drive
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Lexington Drive/Ternbury Drive
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Thornridge Court
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Slade Court
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Kirkton Court
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Brittany Court
November 1-5 – All lanes and driveways open. Backfill, topsoil, and seeding have been completed behind the back of curb. Waiting for grass to establish. Joint sealing has been completed.
Construction Update
October 18-22
Snowden Court has been added to the road program. See schedule below. Restoration is in progress. All lanes and driveways are open on the roads listed below. Additionally, backfill, topsoil, seeding, and joint sealing has been completed; waiting for the grass to establish.
Arlington Dr
Hidden Lane
Crestline Lane
Daylily Drive
Lexington Dr/Ternbury Dr
Thornridge Court
Slade Court
Kirkton Court
Brittany Court
Snowden Court
October 18-22 - Demolition of entire cul-de-sac. Begin base preparation, edge drain installation, and concrete forms.
We would like to thank all the residents for their patience and understanding throughout this construction season. We appreciate all your feedback!
Check out the 2021 Rochester Hills Local Road Program Overview Video and the Road Program #2 Photo Slideshow below!
Construction Update
Restoration is in progress. Although topsoil and seeding have been completed at most locations, grass still needs to establish. SD is working diligently with the contractor to improve lawn restoration. Ongoing maintenance is being performed for topsoil and seed that has been washed away due to heavy rain. Please see an updated construction schedule below.
Arlington Dr
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Hidden Lane
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Crestline Lane
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Daylily Drive
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
v
Lexington Dr/Ternbury Dr
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Thornridge Court
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Slade Court
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Kirkton Court
September 27-October 1 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Brittany Court
September 27-October 1 – All lanes/drives open. Backfill, topsoil, and joint sealing completed. Seeding is to be performed this week, weather permitting.
Construction Update
Restoration is in progress. Although topsoil and seeding have been completed at most locations, grass still needs to establish. SD is working diligently with the contractor to improve lawn restoration. Please complete irrigation repairs ASAP, if applicable. Please see an updated construction schedule below.
Arlington Dr
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Hidden Lane
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Crestline Lane
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Daylily Drive
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Lexington Dr/Ternbury Dr
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Thornridge Court
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Slade Court
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Kirkton Court
September 20-24 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Brittany Court
September 20-24 – All lanes/drives open. Backfill, topsoil, and joint sealing completed. Seeding is anticipated to be performed this week, weather permitting.
Construction Update
Restoration is in progress. Although topsoil and seeding have been completed at most locations, grass still needs to establish. SD is working diligently with the contractor to improve lawn restoration. Please complete irrigation repairs ASAP, if applicable. Please see an updated construction schedule below.
Arlington Dr
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Hidden Lane
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Crestline Lane
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Daylily Drive
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Lexington Dr/Ternbury Dr
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Thornridge Court
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Slade Court
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Kirkton Court
September 13 - 17 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Brittany Court
September 13 - 17 – All lanes open. All driveways open on Monday. Backfilling behind the back of curb has been completed. Sawcutting and sealing are anticipated next week. Restoration to be determined.
Construction Update
Restoration is in progress. Although topsoil and seeding have been completed at most locations, grass still needs to establish. SD is working diligently with the contractor to improve lawn restoration. Please complete irrigation repairs ASAP, if applicable. Please see an updated construction schedule below.
Arlington Dr
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Hidden Lane
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Crestline Lane
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Daylily Drive
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, and joint sealing completed. Seeding to be completed this week. Sidewalk construction on the eastbound side between 430 and 438 is to be completed this week.
Lexington Dr/Ternbury Dr
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Thornridge Court
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Slade Court
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Kirkton Court
September 7 - 10 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Brittany Court
September 7 - 10 – All lanes open. Complete concrete placement on driveways; concrete cure time. Once the concrete has cured, all lanes and driveways will be open. Restoration and joint sealing to be determined.
Construction Update
Restoration is in progress at some locations. Please complete irrigation repairs ASAP, if applicable. Please see an updated construction schedule below.
Arlington Dr
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Hidden Lane
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Crestline Lane>
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Daylily Drive
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, and joint sealing completed. Seeding to be completed this week. Sidewalk construction on the eastbound side between 430 and 438 is to be completed this week.
Lexington Dr/Ternbury Dr
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, and joint sealing completed. Seeding to be completed this week.
Thornridge Court
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Slade Court
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Kirkton Court
August 30-September 3 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed; waiting for the grass to establish.
Brittany Court
August 30-September 3 – All lanes open. Complete concrete placement on two driveways. Complete backfill, topsoil, seeding, and joint sealing.
Construction Update
Restoration is in progress in various locations. Please begin irrigation repairs ASAP, if applicable. Please see an updated construction schedule below.
Arlington Dr
August 23-27 – All lanes and driveways open. Backfill, topsoil, and join sealing completed; seeding to be determined.
Hidden Lane
August 23-27– All lanes and driveways open. Backfill, topsoil, and join sealing completed; seeding to be determined.
Crestline Lane
August 23-27 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed.
Daylily Drive
August 23-27 – All lanes and driveways open. Complete backfill and topsoil behind the back of curb; joint sealing completed.
Lexington Dr/Ternbury Dr
August 23-27 – All lanes and driveways open. Backfill and topsoil completed. Seeding to be completed this week; joint sealing completed.
Thornridge Court
August 23-27 – All lanes and driveways open. Backfill and topsoil completed. Seeding to be completed this week; joint sealing completed.
Slade Court
August 23-27 – All lanes and driveways open. Backfill, topsoil, seeding, and joint sealing completed.
Kirkton Court
August 23-27 – All lanes and driveways open. Backfill and topsoil completed. Seeding to be completed this week; joint sealing completed.
Brittany Court
August 23-27 – Concrete cure time for the southbound lane. Concrete placement on driveways.
Construction Update
Attention Residents:
Backfill behind back of curb for completed roads is expected to begin very soon. Please begin irrigation repairs ASAP. Topsoil and seeding with mulch to follow. We appreciate your patience and cooperation during this construction phase. Please see an updated construction schedule below.
Arlington Dr
August 16-20 – All lanes and driveways open. Complete backfill and begin topsoil behind the back of curb; joint sealing to be determined.
Hidden Lane
August 16-20 – All lanes and driveways open. Complete backfill and begin topsoil behind the back of curb; joint sealing to be determined.
Crestline Lane
August 16-20 – All lanes and driveways open. Complete backfill and begin topsoil behind the back of curb; joint sealing to be determined.
Daylily Drive
August 16-20 – Concrete placement on remaining driveways. Complete backfill and begin topsoil behind the back of curb; joint sealing to be determined.
Lexington Dr/Ternbury Dr
August 16-20 – All lanes and driveways open. Complete backfill and begin topsoil behind the back of curb; joint sealing to be determined.
Thornridge Court
August 16-20 – All lanes and driveways open. Complete backfill and begin topsoil behind the back of curb; joint sealing to be determined.
Slade Court
August 16-20 – All lanes and driveways open. Complete backfill and begin topsoil behind the back of curb; joint sealing to be determined.
Kirkton Court
August 16-20 – All lanes and driveways open. Complete backfill and begin topsoil behind the back of curb; joint sealing to be determined.
Brittany Court
August 16-20 – Northbound lane open. Begin demolition, base preparation, edge drain installation, concrete forms, and concrete placement on the southbound lane.
Construction Update
Attention Residents:
Backfill behind back of curb for completed roads is expected to begin very soon. Please begin irrigation repairs ASAP. Topsoil and seeding with mulch to follow. We appreciate your patience and cooperation during this construction phase. Please see an updated construction schedule below.
Arlington Dr
August 9-13 – All lanes and driveways open. Restoration and joint sealing to be determined.
Hidden Lane
August 9-13 – All lanes and driveways open. Restoration and joint sealing to be determined.
Crestline Lane
August 9-13 – All lanes and driveways open. Restoration and joint sealing to be determined.
Daylily Drive
August 9-13 – Concrete cure time on westbound lane from Buttercup to Mayapple Ct. Expected to be open August 10/August 11. Concrete placement on remaining driveways (anticipated).
Lexington Dr/Ternbury Dr
August 9-13 – All lanes and driveways open. Restoration and joint sealing to be determined.
Thornridge Court
August 9-13 – All lanes and driveways open. Restoration and joint sealing to be determined.
Slade Court
August 9-13 – All lanes and driveways open. Restoration and joint sealing to be determined.
Kirkton Court
August 9-13 – All lanes and driveways open. Restoration and joint sealing to be determined.
Brittany Court
August 9-13 – Concrete cure time on northbound lane. Southbound lane to remain until cul-de-sac and northbound lane are complete.
Construction Update
Attention Residents:
Backfill behind back of curb for completed roads is expected to begin very soon. Please begin irrigation repairs ASAP. Topsoil and seeding with mulch to follow. We appreciate your patience and cooperation during this construction phase. Please see an updated construction schedule below.
Arlington Dr
August 2-6 – All lanes and driveways open. Restoration and joint sealing to be determined.
Hidden Lane
August 2-6 – All lanes and driveways open. Restoration and joint sealing to be determined.
Crestline Lane
August 2-6 – All lanes and driveways open. Restoration and joint sealing to be determined.
Daylily Drive
(One-way eastbound traffic maintained)
August 2-6 – Concrete placement on westbound lane from Buttercup to Mayapple Ct.
Lexington Dr/Ternbury Dr
(Two-way northbound traffic maintained )
August 2-6 – Concrete cure time on Ternbury's southbound lane. Concrete placement on two driveways on Ternbury. Concrete placement on Lexington ( patch).
Thornridge Court
August 2-6 – All lanes and driveways open. Restoration and joint sealing to be determined.
Slade Court
August 2-6 – All lanes open. Concrete cure time on westbound lane.
Kirkton Court
August 2-6 – All lanes open. Concrete placement on southbound lane driveways.
Brittany Court
August 2-6 – Demolition, base preparation, edge drain installation, concrete forms and concrete pour for cul-de-sac and northbound lane continues. Southbound lane to remain until cul-de-sac and northbound lane are complete.
Construction Update
Attention Residents:
Backfill behind back of curb for completed roads is scheduled to begin 7/19/21. Please begin irrigation repairs ASAP. Topsoil and seeding with mulch is scheduled to begin 8/2/21. We appreciate your patience and cooperation during this construction phase.
Due to inclement weather, construction has been slightly delayed. Please see an updated construction schedule below.
Arlington Dr
(Both lanes open to traffic)
July 27– Concrete placement on eastbound Whitney Dr.
Hidden Lane
July 26-30 – All lanes and driveways open. Restoration and joint sealing to be determined.
Crestline Lane
July 26-30 – All lanes and driveways open. Restoration and joint sealing to be determined.
Daylily Drive
(One-way eastbound traffic maintained)
July 26-30 – Demolition from Buttercup to Mayapple Ct. Begin base preparation, edge drain installation, concrete forms, and concrete placement.
Lexington Dr/Ternbury Dr
(One-way westbound traffic maintained)
July 26-30 – Concrete forms and concrete placement on Ternbury’s southbound lane. Removal and replacement of poorly manufactured concrete on Lexington.
Thornridge Court
Entire cul-de-sac open; restoration to be determined.
Slade Court
(All lanes open to traffic)
July 26-30 – Complete westbound lane driveways.
Kirkton Court
(Two-way northbound traffic maintained)
July 26-30 – Concrete placement on southbound lane. Work was delayed last week due to leaking water service repair.
Brittany Court
July 29 – Demolition, base preparation, edge drain installation, and concrete forms (Anticipated).
Construction Update
Due to inclement weather, construction has been slightly delayed. Please see an updated construction schedule below.
Arlington Dr
(Both lanes open to traffic)
July 19-23– Concrete placement on eastbound Whitney Dr.
Hidden Lane
(Two-way traffic will be maintained on south and westbound lanes)
July 19-23 – Concrete cure time.
Crestline Lane
(One-way northbound traffic will be maintained)
July 19-23 – Concrete cure time.
Daylily Drive
(One-way eastbound traffic will be maintained)
July 26 – Demolition from Buttercup to Mayapple Ct; base preparation, edge drain, concrete forms, and concrete placement.
Lexington Drive/Ternbury Drive
(One-way westbound traffic will be maintained)
July 19-23 – Demolition, base preparation, edge drain installation, concrete forms and concrete placement of the southbound lane.
Thornridge Court
Cul-de-sac open at this time. Restoration TBD.
Slade Court
(Two-way eastbound traffic will be maintained)
July 19-23 – Concrete placement of westbound lane.
Kirkton Court
(Two-way southbound traffic will be maintained)
July 19-23 – Concrete placement of southbound lane.
Brittany Court
July 29 – Demolition, base preparation, edge drain installation, and concrete forms (Anticipated).
Construction Update
Due to inclement weather, construction has been slightly delayed. Please see an updated construction schedule below.
Arlington Dr
(Both lanes open to traffic)
July 12-16– Concrete placement on southeast corner of Arlington and Whitney.
Hidden Lane
(Two-way traffic will be maintained on south and westbound lanes)
July 12-16 – Concrete placement on northbound and eastbound lanes.
Crestline Lane
(One-way northbound traffic will be maintained)
July 12-16 – Base preparation, edge drain, concrete forms, concrete placement on southbound lane from Parkland to Crestline Ct.
Daylily Drive
(One-way eastbound traffic will be maintained)
July 12-16 – Demolition from Buttercup to Mayapple Ct; base preparation, edge drain, and concrete forms.
Lexington Drive/Ternbury Drive
(One-way southbound traffic will be maintained on Ternbury; both lanes open on Lexington)
July 12-16 – Demolition of southbound lane may begin late in week, resulting in one way traffic shift to northbound lane of Ternbury.
Thornridge Court
Cul-de-sac open at this time.
Slade Court
(Two-way eastbound traffic will be maintained)
July 12 – Demolition on westbound lane; Base preparation, edge drain, and concrete forms. Concrete placement of westbound lane may begin late in week.
Kirkton Court
(Two-way southbound traffic will be maintained)
July 12-16 – No additional work anticipated this week.
Construction Update
Due to inclement weather and Independence Day holiday, construction has been slightly delayed. Please see an updated construction schedule below.
Arlington Dr
(Both lanes open to traffic)
July 6-9 – Concrete placement on southeast corner of Arlington and Whitney.
Hidden Lane
(Two-way traffic will be maintained on south and westbound lanes)
July 6-9 – Concrete placement on northbound and eastbound lanes.
Crestline Lane
(One-way northbound traffic will be maintained)
July 6-9 – Demolition on southbound lane from Parkland to Crestline Ct; base preparation, edge drain, and concrete forms.
Daylily Drive
(One-way eastbound traffic will be maintained)
July 6-9 – Demolition from Buttercup to Mayapple Ct; base preparation, edge drain, and concrete forms.
Lexington Drive/Ternbury Drive
(One-way westbound traffic will be maintained)
July 6-9 – Concrete placement on Ternbury driveways.
Thornridge Court
(Cul-de-sac open at this time)
Restoration and joint sealing date TBD.
Slade Court
(Two-way eastbound traffic will be maintained)
July 7 – Demolition on westbound lane; Base preparation, edge drain, and concrete forms.
Kirkton Court
(Two-way southbound traffic will be maintained)
July 6-9 – Concrete placement on driveways.
Construction Update
Inclement weather has delayed concrete placement and demolition for all locations. All planned work is weather dependent. Please see an updated construction schedule below.
Arlington Dr
(Both lanes open to traffic)
June 28-July 2 – Demolition on westbound Whitney from Arlington Dr. to approximately 200' west of Arlington Dr. Concrete placement on southeast corner of Arlington and Whitney.
Hidden Lane
(Two-way traffic will be maintained on south and westbound lanes)
June 28-July 2 – Demolition on northbound and eastbound lane, base preparation, edge drain, concrete forms, and concrete placement.
Crestline Lane
(One-way northbound traffic will be maintained)
June 28-July 2 – Demolition on northbound lane from Parkland to Crestline Ct.
Daylily Drive
(One-way eastbound traffic will be maintained)
June 29 – Demolition from Buttercup to Mayapple Ct begins (Anticipated)
Lexington Drive/Ternbury Drive
(One-way westbound traffic will be maintained)
June 28- July 2 – Base preparation, edge drain, concrete forms, and concrete placement on northbound Ternbury and eastbound Lexington.
Thornridge Court
(Cul-de-sac open at this time)
June 28-July 2– Concrete cure time on driveways on the east side of cul-de-sac.
Slade Court
(Two-way westbound traffic will be maintained)
June 28-July 2 – Concrete cure time on eastbound lane; driveway demolition begins (Anticipated).
Kirkton Court
(Two-way southbound traffic will be maintained)
June 28-July 2 – Continue base preparation, edge drain, and concrete forms on northbound lane.
NOTE TO RESIDENTS
Please keep vehicles away from mailboxes and/or out of the mail delivery trucks' path. We appreciate your cooperation during this construction phase.
Construction Update
Please see an updated construction schedule below. Your patience and understanding during this construction project is very much appreciated.
Arlington Dr
(Both lanes open to traffic)
June 21-25 – Demolition on westbound Whitney from Arlington Dr. to approximately 200' west of Arlington Dr begins.
Hidden Lane
(Two-way traffic will be maintained on north and eastbound lanes)
June 21-25 – Demolition on northbound and eastbound lane, base preparation, edge drain, and concrete forms.
Crestline Lane
(One-way northbound traffic will be maintained)
June 21-25 – Concrete cure time on southbound lane driveways.
Daylily Drive
(One-way eastbound traffic will be maintained)
June 21-25 – Concrete placement in two sections: Vardon to Mayapple Ct, and Buttercup to Primrose Dr.
Lexington Drive/Ternbury Drive
(One-way westbound traffic will be maintained)
June 21-25 – Base preparation, edge drain, concrete forms, and concrete placement on northbound Ternbury and eastbound Lexington.
Thornridge Court
(West side of cul-de-sac open at this time)
June 21-25 – Concrete cure time on east side; concrete placement in driveways begins.
Slade Court
(Two-way westbound traffic will be maintained)
June 21-25 – Concrete cure time on eastbound lane; driveway demolition begins.
Kirkton Court
(Two-way southbound traffic will be maintained)
June 21-25 – Demolition of northbound lane, base preparation, edge drain, and concrete forms begins.
NOTE TO RESIDENTS
Please keep vehicles away from mailboxes and/or out of the mail delivery trucks' path. We appreciate your cooperation during this construction phase.
Construction Update
Please see an updated construction schedule below. Your patience and understanding during this construction project is very much appreciated.
Arlington Dr
(Both lanes open to traffic)
June 14-18 – Concrete cure time on driveways.
Hidden Lane
(Two-way traffic will be maintained)
June 14-18 – Concrete placement on westbound lane driveways.
Crestline Lane
(One-way northbound traffic will be maintained)
June 14-18 – Concrete placement on southbound lane driveways.
Daylily Drive
(One-way eastbound traffic will be maintained)
June 14-18 – Base preparation, edge drain, concrete forms and concrete placement in two sections: Vardon to Mayapple Ct, and Buttercup to Primrose Dr.
Lexington Drive/Ternbury Drive
(One-way westbound traffic will be maintained)
June 14 – Demolition of northbound Ternbury and eastbound Lexington begins; base preparation, edge drain, and concrete forms placement.
Thornridge Court
(East side of cul-de-sac open at this time)
June 17 – Concrete placement on east side of cul-de-sac once west side is open to traffic (Anticipated).
Slade Court
(Two-way westbound traffic will be maintained)
June 14 – Concrete placement on eastbound lane.
Kirkton Court
(Two-way southbound traffic will be maintained)
June 18 – Demolition of northbound lane, base preparation, edge drain, and concrete forms begins.
NOTE TO RESIDENTS
Please keep vehicles away from mailboxes and/or out of the mail delivery trucks' path. We appreciate your cooperation during this construction phase.
Construction Update
Please see an updated construction schedule below. Your patience and understanding during this construction project is very much appreciated.
Arlington Dr
(One-way southbound traffic will be maintained)
June 7-11 – Concrete cure time; Driveway preparation and concrete placement.
Hidden Lane
(Two-way traffic will be maintained)
June 7-11 – Westbound and southbound base preparation, edge drain, concrete form and placement begins.
Crestline Lane
(One-way northbound traffic will be maintained)
June 10 – Concrete placement on southbound lane from Drexelgate to Crestline Ct.
Daylily Drive
(One-way eastbound traffic will be maintained)
June 10 – Demolition on westbound lane begins.
Lexington Drive/Ternbury Drive
(One-way eastbound traffic will be maintained)
June 9 – Concrete placement on westbound driveways.
Thornridge Court
(East side of cul-de-sac open at this time)
June 7-11 – Demolition, base preparation, edge drain, concrete form and placement on west side begins.
Slade Court
(Two-way westbound traffic will be maintained)
June 8 – Demolition, base preparation, edge drain, concrete form and placement on east bound lane begins.
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update 1
Updates Coming Soon
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.
David Jackson - Construction Technician
Spalding DeDecker
(248) 844-5400
djackson@sda-eng.com