Final Update
Construction Completed
All the work has been completed! Some restoration areas will be evaluated in the spring and seed will be re-applied where growth is still needed.
We thank all the residents for their coordination and patience during the construction season.
See our 2022 Concrete Program Overview Video below!
Construction Updates
Final Update
Construction Completed
All the work has been completed! Some restoration areas will be evaluated in the spring and seed will be re-applied where growth is still needed.
We thank all the residents for their coordination and patience during the construction season.
See our 2022 Concrete Program Overview Video below!
Project Update 11-11
The streets listed below are open. Homeowners may reinstall irrigation. Restoration has been completed.
Greenleaf Dr
Rochdale Dr
Hillcrest Dr
Dunedin Dr
Intersection of Palm Aire and Dunedin
Cobride Ct and Dr
Quincy Dr
Highsplint Dr
Valley Stream Dr
Olympia Dr
Harlan Ct
Ivy Wood Ct
Whitney Dr
We thank you for your patience and cooperation during the construction season.
Project Update
Construction Update
Week of November 7
The streets listed below are open. Homeowners may reinstall irrigation. Restoration has been completed. Please note that sawcutting and sealing for all streets will continue through the week of November 7.
Greenleaf Dr
Rochdale Dr
Hillcrest Dr
Dunedin Dr
Intersection of Palm Aire and Dunedin
Cobride Ct and Dr
Quincy Dr
Highsplint Dr
Valley Stream Dr
Olympia Dr
Harlan Ct
Restoration will be completed this week on the streets listed below:
Ivy Wood Ct
Whitney Dr
All schedules are weather dependent.
We thank you for your patience and cooperation during the construction season.
Project Update 10-28
Construction Schedule
Please Note: For all streets, sawcutting and sealing will begin the week of October 31st. Depending on weather, this could take up to two weeks to complete.
Greenleaf Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Hillcrest Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Dunedin Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Intersection of Palm Aire and Dunedin
Week of October 31st – Intersection is open. Homeowners may reinstall irrigation. Restoration complete.
Cobridge Ct and Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Quincy Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed.
Highsplint Dr
Week of October 31st – Restoration will begin. Once the concrete is cured, the remaining driveways will be opened.
Valley Stream Dr
Week of October 31st – Entire entrance is open. Restoration complete.
Ivy Wood Ct
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin next week.
Whitney Dr
Week of October 31st – Street is open to traffic. Once the concrete is cured, the driveways will be opened. Restoration is expected to begin the week of November 7th.
Olympia Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed next week.
Harlan Ct
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed next week.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 10-21
Construction Schedule
Greenleaf Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Hillcrest Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Dunedin Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Intersection of Palm Aire and Dunedin
Week of October 24th – Intersection is open. Homeowners may reinstall irrigation. Restoration complete.
Cobridge Ct and Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Quincy Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed.
Highsplint Dr
Week of October 24th – Restoration will begin. Once the concrete is cured, the remaining driveways will be opened.
Valley Stream Dr
Week of October 24th – Entire entrance is open. Restoration complete.
Ivy Wood Ct
Week of October 24th – Street is open to traffic. Once the concrete is cured the driveways will be opened.
Whitney Dr
Week of October 24th – Street is open to traffic. Once the concrete is cured, the driveways will be opened.
Olympia Dr
Week of October 24th – Street and all driveways are open to traffic. Once the concrete is cured, the driveways will be opened. Restoration is complete.
Harlan Ct
Week of October 24th – Street is open to traffic. Once the concrete is cured, the driveways will be opened.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 10-14
Construction Schedule
Greenleaf Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Hillcrest Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Dunedin Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Intersection of Palm Aire and Dunedin
Week of October 17th – Intersection is open. Homeowners may reinstall irrigation. Restoration complete.
Cobridge Ct and Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed.
Quincy Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin
Highsplint Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration may begin.
Valley Stream Dr
Week of October 17th – Entire entrance is open. Restoration complete.
Ivy Wood Ct
(One-way eastbound traffic will be maintained)
Week of October 17th – Complete concrete pour and wait for cure strength for westbound lane. Complete concrete pours for driveways.
Whitney Dr
Week of October 17th – Complete concrete pour and wait for cure strength for southbound lane. Complete concrete pours for driveways.
Olympia Dr
Week of October 17th – Cul-de-sac is open to traffic. Once the concrete is cured, the driveways will be opened. Restoration will begin.
Harlan Ct
Week of October 17th – Cul-de-sac is open to traffic. Driveways will be prepared and poured.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 10-7
Construction Schedule
Greenleaf Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Hillcrest Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Dunedin Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Intersection of Palm Aire and Dunedin
Week of October 10th – Intersection is open. Homeowners may reinstall irrigation. Restoration complete.
Cobridge Ct and Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Quincy Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin
Highsplint Dr
Week of October 10th – Waiting for concrete to cure to strength for northbound lane north of Dawson. All driveways are open for the southbound lane.
Valley Stream Dr
Week of October 10th – Entire entrance is open. Restoration complete.
Ivy Wood Ct
(One-way eastbound traffic will be maintained)
Week of October 10th – Complete concrete pour and wait for cure strength for westbound lane.
Whitney Dr
Week of October 10th – Open to traffic on the northbound lane. Driveways along the northbound lane are waiting for concrete to cure. Pour concrete for the southbound lane.
Olympia Dr
Week of October 10th – Cul-de-sac is open to traffic. Driveways will be prepared and poured.
Harlan Ct
Week of October 10th – Cul-de-sac is open to traffic. Driveways will be prepared and poured.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 9-30
Construction Schedule
Greenleaf Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Hillcrest Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Dunedin Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Intersection of Palm Aire and Dunedin
Week of October 3rd – Intersection is open. Homeowners may reinstall irrigation. Restoration will begin.
Cobridge Ct and Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Quincy Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation.
Highsplint Dr
Week of October 3rd – Concrete pour for northbound lane north of Dawson. All driveways are open for the southbound lane.
Valley Stream Dr
Week of October 3rd – Entire entrance is open. Restoration complete.
Ivy Wood Ct
(One-way eastbound traffic will be maintained)
Week of October 3rd – Base preparation and concrete pour for the westbound lane.
Whitney Dr
Week of October 3rd – Open to traffic on the northbound lane. Begin demolition and pours of driveways along the northbound lane. Begin demolition and base preparation of the southbound lane.
Olympia Dr
Week of October 3rd – Waiting for concrete to attain strength.
Harlan Ct
Week of October 3rd – Concrete pour on the south half of the cul-de-sac. Waiting for concrete to attain strength.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 9-23
Construction Schedule
Greenleaf Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will be complete.
Hillcrest Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Dunedin Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Intersection of Palm Aire and Dunedin
Week of September 26th – Concrete has been poured, waiting for cure strength.
Cobridge Ct and Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation.
Quincy Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation.
Highsplint Dr
Week of September 26th – Begin demolition and base preparation for the northbound lane north of Dawson. All driveways will be open on the southbound lane on Monday.
Valley Stream Dr
Week of September 26th – Entire entrance is open. Restoration complete.
Ivy Wood Ct
(One-way eastbound traffic will be maintained)
Week of September 26th – The eastbound lane and cul-de-sac will be opened.
Begin demolition and base preparation for the westbound lane.
Whitney Dr
Week of September 26th – Complete concrete pour of the northbound lane. Potentially begin demolition and base preparation of the southbound lane.
Olympia Dr
Week of September 26th – Begin concrete pour on the cul-de-sac.
Harlan Ct
Week of September 26th – Complete concrete paving of the cul-de-sac.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 9-16
Week of September 19th – Both sides of the street are open and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed next week as well.
Rochdale DrWeek of September 19th – Both sides of the street are open and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed next week as well.
Hillcrest DrWeek of September 19th – Both sides of the street are open and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Dunedin DrWeek of September 19th – Both sides of the street are open and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Intersection of Palm Aire and DunedinSeptember 22nd – Begin demolition and base preparation.
Cobridge Ct and DrWeek of September 19th – Both sides of the street are open and all driveways are open. Homeowners may reinstall irrigation.
Quincy DrWeek of September 19th – Both sides of the street are open and waiting for driveways to gain strength. Homeowners may reinstall irrigation.
Highsplint DrWeek of September 19th – Both sides of the street are open south of Dawson. Driveways on the southbound side will be poured.
Valley Stream DrWeek of September 19th – Entire entrance is open. Restoration will be completed next week as well.
Ivy Wood Ct(One-way westbound traffic will be maintained)
Week of September 19th – Complete concrete paving for eastbound lane and cul-de-sac and wait for cure strength to be achieved.
Whitney DrWeek of September 19th – Complete demolition, base preparation, and concrete pour of the northbound lane.
Olympia DrWeek of September 19th – Begin demolition and base preparation of the cul-de-sac.
Harlan CtSeptember 22nd – Begin demolition and base preparation of the cul-de-sac.
Project Update 9-9
Project Update 9-2
Project Update 8-26
Project Update 8-19
Project Update 8-12
Project Update 8-5
Project Update 8-2
Project Update 7-29
Project Update 7-22
Project Update 7-15
Project Update 7-8
Project Update 7-1
Project Update 6-24
Project Information
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.
Grady Rollins - Construction Inspector
Spalding DeDecker
grollins@sda-eng.com