The 2023 RH Concrete Road Program Construction has been completed. Check out the program overview below!
Construction Nearly Complete
on Dec 01, 2023
+
December 4 - December 8 Construction Schedule
Long Meadow Lane - Recondition catch basins.
Twin Oaks Court - Recondition catch basins. Complete the sealing and sweeping of the pavement.
Essex Drive - Complete restoration. Sweep pavement.
Cumberland Woods, Kensington Forest, and Wildflower Subdivisions - Complete restoration and irrigation repairs.
Note: This will be the final week of construction. Due to the low temperatures, there may be several locations where sprinkler head issues or restoration will need to be addressed in the spring.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update 11/17
on Nov 17, 2023
+
November 20 - 24 Construction ScheduleLong Meadow Lane - Complete final saw cutting and sealing of pavement joints.
Twin Oaks Court - Complete final saw cutting and sealing of pavement joints.
Essex Drive - Complete the concrete sidewalk ramps on the south side of Grosvenor Drive; Perform final saw cutting and sealing of pavement joints; Complete restoration along Grosvenor Drive.
Note: Please refrain from on-street parking during saw-cutting and sealing activities.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update 11/10
on Nov 10, 2023
+
November 13 - 17 Construction Schedule
Saw cutting and sealing of pavement joints ( weather dependent) on:
Antler Court
Stag Ridge Road
Misty Brook Lane
Slumber Lane
Grovecrest
Rambling Drive
Long Meadow Lane
Jason Circle
Englewood DriveEssex Drive - Continue backfilling behind the curb and restoration. Saw cutting and sealing of pavement joints.
Twin Oaks Court - Continue backfilling behind the curb and restoration. Saw cutting and sealing of pavement joints.
Note: Please refrain from on-street parking during saw-cutting and sealing activities.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update 11/3
on Nov 03, 2023
+
November 6 - 10 Construction Schedule
Saw cutting and sealing of pavement joints ( weather dependent) on:
Antler CourtStag Ridge Road Misty Brook LaneSlumber LaneGrovecrestRambling DriveLong Meadow LaneJason CircleEnglewood DriveEssex Drive - Placing aggregate base, concrete forms, and pouring concrete in the southwest corner of Grosvenor. Continue backfilling behind the curb and restoration.
Twin Oaks Court - Pouring concrete driveways. Continue backfilling behind the curb and restoration.
Note: Please refrain from on-street parking during saw-cutting and sealing activities.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update 10/27
on Oct 27, 2023
+
October 30 - November 3 Construction Schedule
Awaiting final saw cutting and sealing of pavement joints on:
Antler CourtStag Ridge RoadMisty Brook LaneSlumber LaneGrovecrestRambling DriveLong Meadow LaneJason CircleEnglewood DriveEssex Drive - Removing concrete, placing aggregate base, and concrete forms, in the southwest corner of Grosvenor. Restoration.
Twin Oaks Court - Pouring concrete in the westbound lane. Pouring driveways. Begin backfilling behind the curb.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update 10/20
on Oct 20, 2023
+
October 23-27 Construction ScheduleAntler Court - Awaiting final saw cutting and sealing of pavement joints.
Stag Ridge Road - Awaiting final saw cutting and sealing of pavement joints.
Misty Brook Lane - Pouring sidewalk gaps. Awaiting final saw cutting and sealing of pavement joints.
Slumber Lane - Pouring sidewalk gaps. Awaiting final saw cutting and sealing of pavement joints.
Grovecrest - Pouring sidewalk gaps. Awaiting final saw cutting and sealing of pavement joints.
Rambling Drive - Pouring sidewalk gaps. Awaiting final saw cutting and sealing of pavement joints.
Long Meadow Lane - Awaiting final saw cutting and sealing of pavement joints. Pouring concrete sidewalk ramps.
Jason Circle - Awaiting final saw cutting and sealing of pavement joints.
Englewood Drive - Awaiting final saw cutting and sealing of pavement joints.
Essex Drive - Pouring concrete in the southeast corner of Grosvenor. Backfilling curb and placing topsoil.
Twin Oaks Court - Removing concrete, installing edge drain, and placing aggregate base along the westbound lane.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update 10/13
on Oct 13, 2023
+
October 16-20 Construction ScheduleAntler Court - Awaiting final saw cutting and sealing of pavement joints.
Stag Ridge Road - Awaiting final saw cutting and sealing of pavement joints.
Misty Brook Lane - Awaiting final saw cutting and sealing of pavement joints.
Slumber Lane - Awaiting final saw cutting and sealing of pavement joints.
Grovecrest - Awaiting final saw cutting and sealing of pavement joints.
Rambling Drive - Awaiting final saw cutting and sealing of pavement joints.
Long Meadow Lane - Awaiting final saw cutting and sealing of pavement joints. Pouring concrete sidewalk ramps.
Jason Circle - Awaiting final saw cutting and sealing of pavement joints.
Englewood Drive - Awaiting final saw cutting and sealing of pavement joints.
Essex Drive - Removing concrete, placing aggregate base, and concrete forms, in the southeast corner of Grosvenor. Backfilling west side curb.
Twin Oaks Court - Place aggregate base, install forms, and pour concrete in the east half of the cul-de-sac and along the eastbound lane.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update 9/29
on Sep 29, 2023
+
October 2-6 Construction ScheduleAntler Court: Awaiting final saw cutting and sealing of pavement joints.
Stag Ridge Road: Awaiting final saw cutting and sealing of pavement joints.
Misty Brook Lane: Awaiting final saw cutting and sealing of pavement joints.
Slumber Lane: Awaiting final saw cutting and sealing of pavement joints.
Grovecrest: Pouring concrete driveways. Restoration.
Rambling Drive: Pouring concrete driveways. Restoration.
Long Meadow Lane: Pouring concrete sidewalk ramps.
Jason Circle: Awaiting final saw cutting and sealing of pavement joints.
Englewood Drive: Pouring concrete driveways. Backfilling curb.
Essex Drive: Open the southbound lane to traffic. Begin construction in the northbound lane.
Twin Oaks Court: Placing aggregate base, concrete forms, and pouring concrete in the west half of the cul-de-sac. Pouring sidewalk ramps at the Long Meadow Lane intersection.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update 9/22
on Sep 22, 2023
+
September 25 - 29 Construction ScheduleAntler Court: Awaiting final saw cutting and sealing of pavement joints.
Stag Ridge Road: Complete concrete driveways. Continue restoration and cleanup.
Misty Brook Lane: Awaiting final saw cutting and sealing of pavement joints.
Slumber Lane: Awaiting final saw cutting and sealing of pavement joints.
Grovecrest: Open the southbound lane. Begin restoration.
Rambling Drive: Pour concrete driveways. Begin Restoration.
Long Meadow Lane: Placing forms and grading aggregate for sidewalk ramps. Continue restoration.
Jason Circle: Complete restoration.
Englewood Drive: Paving concrete in the westbound/northbound lane.
Essex Drive: Removing concrete, earth excavation, placing aggregate and forms, and pouring concrete in the southbound lane.
Twin Oaks Court: Removing concrete, earth excavation, placing aggregate and forms along the west half of the cul-de-sac.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Schedule 9/15
on Sep 15, 2023
+
September 18 - 22 Construction ScheduleAntler Court: Awaiting final saw cutting and sealing of pavement joints.
Stag Ridge Road: Open the recently poured northbound lane between Fawn Court and Ten Point. Prep driveway for concrete, Continue restoration.
Misty Brook Lane: Awaiting final saw cutting and sealing of pavement joints.
Slumber Lane: Awaiting final saw cutting and sealing of pavement joints.
Grovecrest: Placing aggregate base course, installing concrete forms, and paving concrete in the southbound lane.
Rambling Drive: Paving concrete in the northbound lane.
Long Meadow Lane: Open the recently poured southbound lane, south of Woodfield Way. Begin backfilling the gap behind the curb.
Jason Circle: Paving in the westbound lane east of Quincy Drive. The street should be completely open at the end of the week.
Englewood Drive: Removing pavement, installing edge drain, and placing aggregate base course in the westbound/northbound lane.
Essex Drive: Scheduled to begin September 19th.
Twin Oaks Court: Scheduled to begin September 25th.
Construction Schedule
on Sep 08, 2023
+
September 11- 15 Construction Schedule
Please note that there was a delay in last week's schedule due to rain.
Antler Court: Awaiting final saw cutting and sealing of pavement joints.
Stag Ridge Road: Placing aggregate base course, concrete forms, and paving in the northbound lane between Fawn Court and Ten Point. Complete concrete sidewalk and driveways. Continue restoration.
Misty Brook Lane: Awaiting final saw cutting and sealing of pavement joints.
Slumber Lane: Awaiting final saw cutting and sealing of pavement joints.
Grovecrest: Removing pavement, installing edge drain, and placing aggregate base course in the southbound lane.
Rambling Drive: Placing aggregate base course and installing concrete forms in the northbound lane.
Long Meadow Lane: Paving in the southbound lane north of Twin Oaks Ct and south of Woodfield Way. Pouring concrete driveways.
Jason Circle: Paving in the westbound lane east of Quincy Drive. Continue restoration.
Englewood Drive: Removing pavement, installing edge drain, and placing aggregate base course in the westbound/northbound lane.
Essex Drive: Scheduled to begin September 18th.
Construction Schedule 9/1
on Sep 01, 2023
+
Note: In observance of Labor Day holiday, NO construction work is scheduled for Monday, September 4th.
September 5th - 8th Construction ScheduleAntler Court: Completed.
Stag Ridge Road: Placing aggregate base course, concrete forms, and paving in the northbound lane between Fawn Court and Ten Point.
Misty Brook Lane: No work.
Slumber Lane: No work.
Grovecrest: Removing pavement, placing aggregate base course, and concrete forms in the southbound lane.
Rambling Drive: Removing pavement, placing aggregate base course, and concrete forms in the northbound lane.
Long Meadow Lane: Paving in the southbound lane north of Twin Oaks Ct and south of Woodfield Way. Pouring concrete driveways.
Jason Circle: Removing pavement, placing aggregate base course, Concrete forms, and paving in the westbound lane east of Quincy Drive. Pouring concrete driveways.
Englewood Drive: Waiting for concrete to obtain strength.
The construction schedule is weather dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Schedule 8/25
on Aug 25, 2023
+
August 28 - September 1 Construction ScheduleAntler Court: Completed.
Stag Ridge Road: Remove pavement in the northbound lane north of Fawn Court.
Misty Brook Lane: Continue restoration.
Slumber Lane: Backfilling gaps behind the back of the curb. Begin restoration.
Grovecrest: Complete paving in the northbound lane between Slumber Lane and Misty Brook Lane.
Rambling Drive: Open the southbound lane to traffic.
Long Meadow Lane: Removing pavement, earth excavation, and installing edge drain in the southbound lane north of Twin Oaks Ct and south of Woodfield Way.
Jason Circle: Remove westbound pavement east of Quincy Drive.
Englewood Drive: Placing aggregate base, concrete forms, and paving in the southbound/eastbound lane.
Construction Schedule 8/18
on Aug 18, 2023
+
August 21- 25 Construction ScheduleAntler Court: Completed.
Stag Ridge Road: Remove pavement in the northbound lane north of Fawn Court.
Misty Brook Lane: Backfilling gaps behind the back of the curb and begin restoration.
Slumber Lane: Pouring driveways along the north side of the street. Backfilling gaps behind the back of the curb.
Grovecrest: Placing aggregate base course, Concrete forms, and paving in the northbound lane between Slumber Lane and Misty Brook Lane.
Rambling Drive: Paving concrete in the southbound lane between Slumber Lane and Misty Brook Lane.
Long Meadow Lane: Removing pavement, earth excavation, and installing edge drain in the southbound lane north of Twin Oaks Ct and south of Woodfield Way.
Jason Circle: Complete paving in the eastbound lane. Waiting for concrete in the eastbound/northbound lane to obtain strength. May remove westbound pavement east of Quincy Drive at the end of the week.
Englewood Drive: Removing pavement, earth excavation, installing edge drain, and placing aggregate base in the southbound/eastbound lane.
Construction Schedule 8/11
on Aug 11, 2023
+
August 14 - 18 Construction ScheduleAntler Court: Completed.
Stag Ridge Road: Concrete paving in the northbound lane south of Fawn Court.
Misty Brook Lane: Backfilling gaps behind the back of the curb.
Slumber Lane: Pouring driveways along the north side of the street. Backfilling gaps behind the back of the curb.
Grovecrest: Installing edge drain and placing aggregate base course in the northbound lane between Slumber Lane and Misty Brook Lane.
Rambling Drive: Placing aggregate base course and installing concrete forms in the southbound lane between Slumber Lane and Misty Brook Lane.
Long Meadow Lane: Complete concrete paving in the northbound lane. Removing pavement and earth excavation in the southbound lane north of Twin Oaks Ct and south of Woodfield Way.
Jason Circle: Fine grading aggregate base course, installing concrete forms, and paving in the eastbound/northbound lane.
Englewood Drive: Removing pavement, earth excavation, and installing edge drain in the southbound/eastbound lane.
The construction schedule is weather dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Schedule 8/4
on Aug 04, 2023
+
August 7 - 11 Construction ScheduleAntler Court: Beginning restoration.
Stag Ridge Road: Placing aggregate base and installing concrete forms in the northbound lane south of Fawn Court.
Misty Brook Lane: Complete paving in the eastbound lane. Wait for cure time and open to traffic.
Slumber Lane: Concrete paving in the westbound lane.
Grovecrest: Begin removing pavement in the northbound lane between Slumber Lane and Misty Brook Lane.
Rambling Drive: Begin removing pavement in the southbound lane between Slumber Lane and Misty Brook Lane.
Long Meadow Lane: Concrete paving in the northbound lane. Pour concrete driveways along the west side of the street.
Jason Circle: Removing concrete, earth excavation, and installing edge drain in the eastbound/northbound lane. Pouring concrete driveways on the west side of the street.
The construction schedule is weather dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Schedule 7/28
on Jul 28, 2023
+
July 31- August 4 Construction ScheduleAntler Court: Backfilling curb in preparation for restoration.
Stag Ridge Road: Concrete removal, earth excavation, and installing edge drain in the northbound lane south of Fawn Court.
Misty Brook Lane: Paving concrete in the eastbound lane.
Slumber Lane: Placing aggregate base and installing concrete forms in the westbound lane.
Long Meadow Lane: Placing aggregate base and installing concrete forms in the northbound lane.
Jason Circle: Waiting for concrete to cure in the southbound/westbound lane.
The construction schedule is weather dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Schedule 7/21
on Jul 21, 2023
+
July 24-28 Construction ScheduleAntler Court: Waiting for new concrete to obtain strength.
Stag Ridge Road: Waiting for new concrete to obtain strength.
Misty Brook Lane: Placing aggregate base and installing concrete forms in the eastbound lane.
Slumber Lane: Installing edge drain and placing aggregate base in the westbound lane.
Long Meadow Lane: Removing concrete, earth excavation, and installing edge drain in the northbound lane.
Jason Circle: Fine grading aggregate base and paving concrete in the southbound/westbound lane.
The construction schedule is weather dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Schedule 7/17
on Jul 14, 2023
+
July 17-21 Construction Schedule
Antler Court: Concrete paving in the eastbound lane, west of Stag Ridge Road.
Stag Ridge Road: Concrete paving in the southbound lane, south of Antler Court and at the Ten Point intersection.
Misty Brook Lane: Pavement removal, earth excavation, installing edge drain, and placing aggregate base in the eastbound lane.
Slumber Lane: Pavement removal, earth excavation, and installing edge drain in the westbound lane.
Long Meadow Lane: Waiting for new concrete to obtain strength in the southbound lane between Twin Oaks Court and Woodfield Way.
Jason Circle: Placing aggregate base and installing concrete forms in the southbound/westbound lane.
The construction schedule is weather dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Schedule 7/10
on Jul 10, 2023
+
July 10-14 Construction Schedule
Antler Court: Installing edge drain and placing the aggregate base in the eastbound lane west of Stag Ridge Road.
Stag Ridge Road: Installing edge drain and placing the aggregate base in the southbound lane south of Antler Court and at the Ten Point intersection.
Misty Brook Lane: Complete the concrete paving in the westbound lane.
Slumber Lane: Placing and grading aggregate base course and paving concrete in the eastbound lane.
Long Meadow Lane: Placing the aggregate base, concrete forms, and paving in the southbound lane between Twin Oaks Court and Woodfield Way.
Jason Circle: Removing pavement, earth excavation, and installing edge drain in the southbound/westbound lane.
The construction schedule is weather dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Schedule 6-30
on Jun 30, 2023
+
The contractor is off for the 4th of July Holiday starting Saturday, July 1 to Tuesday, July 4Antler Court: Begin removal of the eastbound lane west of Stag Ridge Road, earth excavation, and begin installing edge drain.
Stag Ridge Road: Begin removal of the southbound lane south of Antler Court.
Misty Brook Lane: Continuation of placement and grading of aggregate base course and concrete paving in the westbound lane.
Slumber Lane: Begin installing forms for concrete paving and placing aggregate base.
Long Meadow Lane: Begin installing edge drain, earth excavation, and placing the aggregate base in the southbound lane between Twin Oaks Court and Woodfield Way.
Jason Circle: Begin removing pavement in the westbound lane near Quincy Drive later in the week.
Construction Schedule 6-23
on Jun 23, 2023
+
Antler Court: Waiting for concrete to obtain strength. Will begin removal of the eastbound lane late in the week.
Stag Ridge Road: Waiting for concrete to obtain strength. Begin removing the southbound lane south of Antler Court late in the week.
Misty Brook Lane: Complete pavement removal in the westbound lane; install edge drain, aggregate base; place forms, and begin paving.
Slumber Lane: Begin pavement removal in the eastbound lane; install edge drain and aggregate base.
Long Meadow Lane: Begin pavement removal in the southbound lane between Twin Oaks Court and Woodfield Way and install edge drain.
Construction Schedule 6-19
on Jun 16, 2023
+
June 19-23 Construction ScheduleAntler Court: Paving the cul-de-sac and the westbound lane.
Stag Ridge Road: Placing aggregate base and paving in the southbound lane between Tenpoint and Antler Court.
Misty Brook Lane: Removing pavement in the westbound lane, installing edge drain, and installing aggregate base.
Slumber Lane: Removing pavement, installing edge drain and aggregate base course on the eastbound lane.
The construction schedule is weather dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Begins June 12
on Jun 09, 2023
+
City of Rochester Hills
2023 Concrete Road Program
Concrete replacement locations: Long Meadow Ln, Englewood Dr, Jason Cir, Misty Brook Ln, Rambling Dr, Grovecres, Slumber Ln, Antler Ct, and Stag Ridge Rd. Sidewalk replacement is anticipated in: 1) Cumberland Woods sub 2) Kensington Forest sub 3) Rookery Woods sub 4) Wildflower sub
Construction Update
June 9, 2023
Construction Begins Monday, June 12, 2023!
Pavement removal is scheduled to begin on Monday, June 12 at 7 a.m. starting on southbound Stag Ridge (Ten Point Dr. to Antler Ct.) and westbound Antler Court (including the cul-de-sac).
Reminder: Vehicles must be removed from driveways prior to construction.
The construction schedule is weather dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Notice
on May 23, 2023
+
Sign up HERE to receive updates on project progress, schedule changes, weather delays, detours, and other relevant information. Concrete replacement locations: Long Meadow Ln, Englewood Dr, Jason Cir, Misty Brook Ln, Rambling Dr, Grovecres, Slumber Ln, Antler Ct, and Stag Ridge Rd. Sidewalk replacement is anticipated in: 1) Cumberland Woods sub 2) Kensington Forest sub 3) Rookery Woods sub 4) Wildflower sub
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.