Latest Update
Construction Update
Aug 30, 2024
The project is completed.
We thank all the residents for their patience and cooperation during construction.
The contractor will continue to address deficient items in the North Brooklands Subdivision.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
Check out the project overview below!
Read More
Construction Updates
Construction Update
on Aug 30, 2024
+
The project is completed.
We thank all the residents for their patience and cooperation during construction.
The contractor will continue to address deficient items in the North Brooklands Subdivision.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
Check out the project overview below!
Construction Update
on Aug 23, 2024
+
Construction Schedule Week of August 26th, 2024
North Brooklands Subdivision
Working on deficient items throughout the subdivision.
Adams Rd Pathway
Complete restoration along the HMA pathway.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update
on Aug 16, 2024
+
Construction Schedule: Week of August 16th, 2024
North Brooklands Subdivision:
Working on deficient items throughout the subdivision.
Market Place Circle:
Completed.
Adams Rd Pathway:
1) Fill gaps at new sidewalk ramps.
2) Continue restoration along HMA Pathway.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update
on Aug 09, 2024
+
Construction Schedule: Week of August 12th, 2024
North Brooklands Subdivision:
Awaiting a date for Punch List item repairs throughout the subdivision.
Market Place Circle:
Completed.
Adams Rd Pathway:
1) Continuing pouring concrete curb and gutter at proposed side walk ramps.
2) Continue pouring concrete for the new sidewalk and ramps.
3) Continue restoration along the HMA pathway.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update
on Aug 02, 2024
+
Construction Schedule: Week of August 5th, 2024
North Brooklands Subdivision:
Repair punch list items throughout the subdivision.
Market Place Circle:
Completed.
Adams Rd Pathway:
1) Preparing subgrade for new sidewalk and ramps.
2) Pour concrete for the new sidewalk and ramps.
3) Continue restoration along the HMA pathway.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Updates
on Jul 26, 2024
+
Construction Schedule: Week of July 26th, 2024
North Brooklands Subdivision:
Complete restoration of lawns throughout the subdivision.
Market Place Circle:
Restoration continues behind miscellaneous curb repair areas.
Adams Rd Pathway:
1) Continue removing existing concrete ramps and curb in preparation for new concrete ramps.
2) Preparing subgrade for new sidewalk and ramps.
3) Begin restoration along the HMA pathway.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update
on Jul 19, 2024
+
Construction Schedule: Week of July 22nd, 2024
North Brooklands Subdivision:
Restoration of lawns continues throughout the subdivision.
Market Place Circle:
Restoration to follow after North Brooklands subdivision is complete.
Adams Rd Pathway:
1) Removing the remaining concrete ramps and curb in preparation for new concrete ramps.
2) Possibly begin pouring concrete curb and gutter.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update
on Jul 12, 2024
+
Construction Schedule: Week of July 15, 2024
North Brooklands Subdivision:
Restoration of lawns continues throughout the subdivision.
Market Place Circle:
Restoration to follow after North Brooklands subdivision is complete.
Adams Rd Pathway:
1) Placing aggregate base and grading on HMA Pathway.
2) Pave asphalt overlay along the entire Pathway.
3) Remove remaining concrete ramps and curb in preparation for new concrete ramps.
The construction schedule is weather-dependent.
For questions please contact Grady Rollins, Project Manager.
734-968-8633 | grollins@sda-eng.com
We are looking forward to working with you toward a successful construction project!
Construction Update
on Jul 05, 2024
+
During the week of July 5th:
North Brooklands Subdivision -
Continue restoring lawns throughout the subdivision.
Market Place Circle -
Restoration to follow after North Brooklands subdivision is complete.
Adams Rd Pathway -
1.) Removing asphalt pathway in various locations.
2.) Performing pavement repair and grading on HMA pathway.
3.) Begin asphalt paving.
Construction Update
on Jun 28, 2024
+
During the week of June 28th:
North Brooklands Subdivision -
Continue restoring lawns throughout the subdivision.
Market Place Circle -
Restoration to follow after North Brooklands subdivision is complete.
Adams Rd Pathway -
1.) Milling asphalt pathway in various locations.
2.) Performing pavement repair on HMA pathway .
3.) Adjusting manhole castings.
4.) Paving is tentatively scheduled for the week of July 8th.
No work will be done July 4th - 7th.
Construction Update
on Jun 21, 2024
+
During the week of June 21st:
North Brooklands Subdivision -
Continue restoring lawns throughout the subdivision.
Market Place Circle -
1.) Open all lanes to traffic.
2.) Continue restoration at curb replacement areas.
Adams Rd Pathway -
1.) Begin milling the asphalt pathway in various locations.
2.) Paving is tentatively scheduled for the week of July 8th, 2024.
Construction Update
on Jun 14, 2024
+
During the week of June 14th:
North Brooklands Subdivision -
Restoration of lawns throughout the subdivision will take place depending on the hot temperatures predicted next week.
Market Place Circle -
1.) Milling of the asphalt surface in Phase 2.
2.) Pave asphalt in Phase 2.
3.) Open lanes to traffic.
Adams Rd Pathway -
1.) Replace the culvert at Tienken Road.
2.) Begin removing select curb and gutter at sidewalk ramps.
Construction Update
on Jun 07, 2024
+
During the week of June 7th:
North Brooklands Subdivision -
1.) Begin restoration of lawns throughout the subdivision mid-week.
2.) Perform repairs of deficient items.
Market Place Circle -
1.) Pour concrete for curb and gutter repairs in Phase 2 construction area.
2.) The asphalt surface will be milled in Phase 2 at the end of the week, dependent on the strength of the new concrete.
3.) Pave asphalt in Phase 2 at the end of the week, dependent on the strength of the new concrete.
4.) Begin lawn restoration at the curb and gutter repair areas.
Adams Rd Pathway - The anticipated start date is mid-June.
Construction Update
on May 31, 2024
+
During the week of June 3rd:
North Brooklands Subdivision -
1.) Complete asphalt paving. Signs will be placed at the each entrance of the paving area on paving days.
2.) Complete the paving of asphalt spillways for drainage throughout the subdivision.
Market Place Circle -
1.) Milling of the asphalt surface in Phase 1 begins Monday.
2.) Pave asphalt in Phase 1 construction area.
3.) Switch traffic to Phase 2 construction detour mid week.
4.) Begin removal and replacement of the damaged concrete curb and gutter within the Phase 2 construction area.
Adams Rd Pathway - The anticipated start date is mid-June.
Construction Update
on May 24, 2024
+
During the week of May 27th:
No work will be performed on Memorial Day.
North Brooklands Subdivision -
1.) Asphalt paving continues. Signs will be placed at each entrance of the paving area on paving days.
2.) Paving asphalt spillways for drainage throughout the subdivision.
Market Place Circle -
1.) The construction detour for Phase 1 is in place.
2.) Crews will complete the removal and replacement of the damaged concrete curb and gutter within the Phase 1 construction area.
3.) Milling of the asphalt surface begins at the end of the week or early the following week.
Adams Rd Pathway - The anticipated start date is mid-June.
Construction Update
on May 17, 2024
+
During the week of May 20th:
North Brooklands Subdivision -
1.) Crews will continue pavement crack repairs throughout the subdivision.
2.) Asphalt paving continues. Signs will be placed at each entrance of the paving area on paving days.
Market Place Circle -
1.) Construction detour for Phase 1 is in place.
2.) Crews will continue removing and replacing the damaged curb within the Phase 1 construction area.
Adams Rd Pathway - No work.
Construction Update
on May 10, 2024
+
During the week of May 13th:
North Brooklands Subdivision - Crews will complete the milling of 1-1/2" of existing asphalt off of the pavement surface. Pavement crack repairs will continue throughout the subdivision. Paving begins mid-week. Signs will be placed at each entrance of the subdivision on paving days.
Market Place Circle - Detour signing will be installed on Monday for Phase 1. Crews will begin sawcutting and removing the damaged curb in the Phase 1 construction area.
Adams Rd Pathway - No work.
Construction Update
on May 03, 2024
+
North Brooklands Subdivision - During the week of May 6th, crews will be milling 1-1/2" of existing asphalt off of the pavement surface. The operation is scheduled to start on Hessel Ave, located in the southeast corner of the subdivsion, and progress north and west. Pavement crack repairs will also begin this week following the pavement milling operation.
Market Place Circle - No work. The tentative start date is May 13th.
Adams Rd Pathway - No work.
Construction Update
on Apr 26, 2024
+
Construction Notice
on Apr 19, 2024
+
Construction is scheduled to begin starting the week of 4/22.
North Brooklands Subdivision - Beginning the week of April 22nd, crews will be working on curb repair, asphalt spillway removals, and manhole repairs throughout the entire subdivision.
Market Place Circle - No work.
Adams Rd Pathway - No work.
Updates Coming Soon
on Mar 29, 2024
+
Stay tuned for construction updates for the Rochester Hills Asphalt Road Program! Locations include: Part A: North Brooklands Subdivision Resurfacing, Part B: Market Place Circle Rehabilitation, Part C: Adams Road (West side) Pathway Rehab (Tienken to Dutton)
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.