Latest Update

Construction Update

Sep 12, 2025
For the week of September 15th:

Eddington Boulevard (Phase 1-4) Farnborough to Essex
  1. The new pavement is open to traffic.
  2. Speed hump installation to be determined.
Flanders Drive  
  1. The new pavement is open to traffic.
  Sugar Pine Road (Phase 1-4) Walton to Tanglewood
  1. The new pavement is open to traffic.
  Sanctuary Blvd at South Blvd 
  1. Completed.
 
Pheasant Ring/Eagle Drive (Phase 1-4) 
  1. The new pavement is open to traffic.
  2. Continue restoration.
  Pheasant Ring (added segment east of Pheasant Ring Court)
  1. The new pavement is open to traffic.
  2. Remove and replace remaining concrete at Pheasant Ring Court.
  3. Continue restoration.
 
Cedar Shake/Lakewood Drive (Phase 1-4)
  1. The new pavement is open to traffic.
  2. Restoration is complete.
 
Independence Drive/Court (Phase 1-3)
  1. The new pavement is open to traffic.
  Independence Drive/Court (Phase 4) 
  1. Removing concrete and earth excavation.
  2. Installing edge drain and placing aggregate base.
  3. Pave remaining concrete.
 
Charlwood Drive  
  1. Open to traffic mid-week.
  2. Complete concrete in the southwest corner of Charlwood Dr & Whitehouse Ct to complete the intersection.
  Sidewalk replacement Program
  1. Concrete sidewalk repairs are complete Rookery woods. Restoration to follow.
  2. Pouring concrete sidewalk in the Clear Creek subdivision.
  3. Pouring concrete sidewalk in the East Hampton subdivision.

Pavement Removal.


Fresh Pavement.
Read More