Sidewalk Replacement Program
Restoration will take place in the Rookery Woods, Clear Creek, and East Hampton subdivisions.
Construction Update
on Sep 26, 2025
+
For the Week of September 29th:
Residents: Please try to park all vehicles in your driveway this week during the pavement joint sealing activities on your street.
Eddington Boulevard (All phases) Farnborough to Essex
Site cleanup.
Saw cutting and sealing pavement joints.
Speed hump installation early October.
Flanders Drive
Saw cutting and sealing pavement joints.
Sugar Pine Road (All phases) Walton to Tanglewood
Site cleanup.
Saw cutting and sealing pavement joints.
Sanctuary Blvd at South Blvd
Complete.
Pheasant Ring/Eagle Drive (All phases)
Site cleanup.
Saw cutting and sealing pavement joints.
Cedar Shake/Lakewood Drive (All phases)
Site cleanup.
Saw cutting and sealing pavement joints.
Independence Drive/Court (All phases)
New pavement is open to traffic.
Site cleanup.
Saw cutting and sealing pavement joints.
Backfilling curb and working on restoration.
Charlwood Drive
Site cleanup.
Saw cutting and sealing pavement joints.
Sidewalk Replacement Program
Concrete sidewalk repairs are complete - Rookery woods. Restoration to follow.
Concrete sidewalk repairs are complete - Clear Creek subdivision. Restoration to follow.
Concrete sidewalk repairs are complete - East Hampton subdivision. Restoration to follow.
Eddington Boulevard at Farnborough Drive - September 26th.
Construction Update
on Sep 19, 2025
+
For the week of September 22nd:
Eddington Boulevard (Phase 1-4) Farnborough to Essex
The new pavement is open to traffic.
Speed humps to be installed in early October.
Flanders Drive
The new pavement is open to traffic.
Sugar Pine Road (Phase 1-4) Walton to Tanglewood
The new pavement is open to traffic.
Sanctuary Blvd at South Blvd
Completed.
Pheasant Ring/Eagle Drive (Phase 1-4)
The new pavement is open to traffic.
Continue restoration.
Pheasant Ring (added segment east of Pheasant Ring Court)
The new pavement is open to traffic.
Waiting for concrete to obtain strength in the southwest corner of Pheasant Ring Court.
Continue restoration.
Cedar Shake/Lakewood Drive (Phase 1-4)
The new pavement is open to traffic.
Restoration is complete.
Independence Drive/Court (Phase 1-3)
The new pavement is open to traffic.
Backfilling the curb and working on restoration.
Independence Drive/Court (Phase 4)
Waiting for concrete to obtain strength.
Pave remaining concrete driveways.
Backfilling the curb and working on restoration.
Charlwood Drive
Open to traffic.
Waiting for concrete to obtain strength in the southwest corner of Charlwood Drive and Whitehouse Court.
Complete restoration.
Sidewalk replacement Program
All concrete sidewalk repairs are complete in the Rookery Woods, Clear Creek, and East Hampton subdivisions. Restoration to follow.
Construction Update
on Sep 12, 2025
+
For the week of September 15th:
Eddington Boulevard (Phase 1-4) Farnborough to Essex
The new pavement is open to traffic.
Speed hump installation to be determined.
Flanders Drive
The new pavement is open to traffic.
Sugar Pine Road (Phase 1-4) Walton to Tanglewood
The new pavement is open to traffic.
Sanctuary Blvd at South Blvd
Completed.
Pheasant Ring/Eagle Drive (Phase 1-4)
The new pavement is open to traffic.
Continue restoration.
Pheasant Ring (added segment east of Pheasant Ring Court)
The new pavement is open to traffic.
Remove and replace remaining concrete at Pheasant Ring Court.
Continue restoration.
Cedar Shake/Lakewood Drive (Phase 1-4)
The new pavement is open to traffic.
Restoration is complete.
Independence Drive/Court (Phase 1-3)
The new pavement is open to traffic.
Independence Drive/Court (Phase 4)
Removing concrete and earth excavation.
Installing edge drain and placing aggregate base.
Pave remaining concrete.
Charlwood Drive
Open to traffic mid-week.
Complete concrete in the southwest corner of Charlwood Dr & Whitehouse Ct to complete the intersection.
Sidewalk replacement Program
Concrete sidewalk repairs are complete Rookery woods. Restoration to follow.
Pouring concrete sidewalk in the Clear Creek subdivision.
Pouring concrete sidewalk in the East Hampton subdivision.
Construction Update
on Aug 08, 2025
+
For the week of August 11th, 2025Eddington Boulevard (Phases 1 & 2) Farnborough to Windrift
New pavement is open to traffic.
Eddington Boulevard (Phase 3 - westbound) Farnborough to Windrift
New pavement is open to traffic.
Continue restoration.
Eddington Boulevard (Phase 4 - eastbound) Farnborough to Windrift
Open the new pavement to traffic.
Continue restoration.
Flanders Drive (Phase 1 & 2)
New pavement is open to traffic.
Sugar Pine Road (Phases 1 & 2) Walton to Black Maple
New pavement is open to traffic.
Sugar Pine Road (Phase 3) Black Maple to Tanglewood
New pavement is open to traffic.
Continue restoration.
Sugar Pine Road (Phase 4) Black Maple to Tanglewood
Open to new pavement.
Pour driveways.
Continue restoration.
Sanctuary Blvd at South Blvd
Complete.
Pheasant Ring/Eagle Drive (Phases 1 & 2)
New pavement is open to traffic.
Pheasant Ring/Eagle Drive (Phase 3) - House 2979 to 2931
Installing aggregate base and concrete forms.
Begin paving.
Cedar Shake/Lakewood Drive (Phases 1 & 2)
New pavement is open to traffic.
Cedar Shake/Lakewood Drive (Phase 3)
Placing aggregate base and installing concrete forms.
Begin paving.
Independence Drive/Court (Phase 1)
New pavement is open to traffic .
Independence Drive/Court (Phase 2)
Begin removing pavement and earth excavation.
Sidewalk Replacement Program
Begin removals in the Rookery Woods subdivision.
Check out our video update from last week!
Construction Update
on Aug 29, 2025
+
Construction schedule for the week of September 1st:
No work Labor Day Monday 9/1/25Eddington Boulevard (Phase 1-4) Farnborough to Essex
The new pavement is open to traffic.
Speed Hump installation TBD.
Flanders Drive
New pavement is open to traffic.
Sugar Pine Road (Phase 1-4) Walton to Tanglewood
New pavement is open to traffic.
Sanctuary Blvd at South Blvd
Complete.
Pheasant Ring/Eagle Drive (Phase 1-3)
New pavement is open to traffic.
Pheasant Ring (Phase 4 southbound)
Continue paving the final section of concrete
Pheasant Ring (added segment, eastbound) Pheasant Ring Court to house 2946
Paving the final section of concrete.
Cedar Shake/Lakewood Drive (Phase 1 & 2)
New pavement is open to traffic.
Cedar Shake Drive (Phase 3)
Open new pavement to traffic.
Cedar Shake Drive (Phase 4)
Placing aggregate base and installing concrete forms.
Paving remaining concrete.
Independence Drive/Court (Phase 1)
New pavement is open to traffic.
Independence Drive/Court (Phase 2)
New pavement is open to traffic.
Independence Drive/Court (Phase 3)
Installing Edge Drain and placing aggregate base.
Charlwood Drive
Removing pavement and earth excavation.
Sidewalk replacement Program
Concrete sidewalk repairs are complete Rookery woods. Restoration to follow.
Placing sand over recently installed edge drain pipe within excavated trench. Southbound Independence Drive.
Compacting the sand backfill over edge drain ahead of aggregate base placement. Westbound Cedar Shake Drive.
Construction Update
on Aug 22, 2025
+
For the week of August 25th, 2025:Eddington Boulevard (Phase 1-4) Farnborough to Essex
The new pavement is open to traffic.
Continue restoration.
Flanders Drive
New pavement is open to traffic.
Sugar Pine Road (Phase 1-4) Walton to Tanglewood
New pavement is open to traffic.
Continue restoration.
Sanctuary Blvd at South Blvd
Complete.
Pheasant Ring/Eagle Drive (Phase 1-3)
New pavement is open to traffic.
Pheasant Ring (Phase 4 southbound)
Trimming aggregate base and placing concrete forms.
Begin paving the final section of concrete.
Pheasant Ring (added segment, eastbound) Pheasant Ring Court to house 2946
Trimming aggregate base and placing concrete form.
Begin paving the final section of concrete.
Cedar Shake/Lakewood Drive (Phase 1 & 2)
New pavement is open to traffic.
Cedar Shake Drive (Phase 3)
Open new pavement to traffic.
Cedar Shake Drive (Phase 4)
Removing pavement and earth excavation.
Installing edge drain and aggregate base.
Independence Drive/Court (Phase 1)
New pavement is open to traffic.
Independence Drive/Court (Phase 2)
Allow cure time for new concrete.
Independence Drive/Court (Phase 3)
Begin removing pavement and earth excavation
Sidewalk Replacement Program
Concrete sidewalk repairs are complete Rookery woods. Restoration to follow.
Construction Update
on Aug 15, 2025
+
For the week of August 18th, 2025Eddington Boulevard (Phases 1 & 2) Farnborough to Windrift
New pavement is open to traffic.
Eddington Boulevard (Phases 3 & 4) West of Farnborough to Windrift
New pavement is open to traffic.
Continue restoration.
Flanders Drive (Phase 1 & 2)
New pavement is open to traffic.
Sugar Pine Road (Phases 1 & 2) Walton to Black Maple
New pavement is open to traffic.
Sugar Pine Road (Phases 3 & 4) Black Maple to Tanglewood
New pavement is open to traffic.
Continue restoration.
Sanctuary Blvd at South Blvd
Complete.
Pheasant Ring/Eagle Drive (Phases 1 & 2)
New pavement is open to traffic.
Pheasant Ring (Phase 3 - northbound)
New pavement is open to traffic.
Pheasant Ring (Phase 4 - southbound)
Begin removing pavement and earth excavation.
Install edge drain and aggregate base.
Pheasant Ring (Phase 3 - westbound): House 2979 to 2931
New pavement is open to traffic.
Pheasant Ring (Phase 4 - westbound): Pheasant Ring Court to House 2946
Begin removing pavement and earth excavation.
Cedar Shake/Lakewood Drive (Phases 1,2, & 3)
New pavement is open to traffic.
Cedar Shake/Lakewood Drive (Phase 4)
Begin removing pavement and earth excavation.
Independence Drive/Court (Phase 1)
New pavement is open to traffic .
Independence Drive/Court (Phase 2)
Installing edge drain and aggregate base south of Dutton Road.
Begin paving.
Sidewalk Replacement Program
Concrete sidewalk repairs are complete in the Rookery Woods. Restoration to follow.
Construction Update
on Sep 05, 2025
+
Construction schedule for the week of September 8th:
Eddington Boulevard (Phase 1-4) Farnborough to Essex
The new pavement is open to traffic.
Speed Hump installation TBD.
Flanders Drive
New pavement is open to traffic.
Sugar Pine Road (Phase 1-4) Walton to Tanglewood
New pavement is open to traffic.
Sanctuary Blvd at South Blvd
Complete.
Pheasant Ring/Eagle Drive (Phase 1-3)
New pavement is open to traffic.
Continue restoration.
Pheasant Ring (Phase 4 southbound)
Allow cure time for final section of new pavement.
Pheasant Ring (added segment, eastbound) Pheasant Ring Court to house 2946
Allow cure time for final section of new pavement.
Cedar Shake/Lakewood Drive (Phases 1, 2 & 3)
New pavement is open to traffic.
Continue restoration.
Cedar Shake Drive (Phase 4)
Allow for cure time for final section of new pavement.
Independence Drive/Court (Phases 1 & 2)
New pavement is open to traffic.
Independence Drive/Court (Phase 3)
Paving concrete.
Allow cure time for new concrete.
Charlwood Drive
Place aggregate base and concrete forms.
Pave concrete.
Sidewalk Replacement Program
Concrete sidewalk repairs are complete in Rookery woods. Restoration to follow.
Begin removing sidewalk in the Clear Creek subdivision.
East Hampton TBD.
Construction Update
on Aug 01, 2025
+
For the week of August 4th, 2025Eddington Boulevard (Phase 1 & 2) Farnborough to Windrift
New pavement is open to traffic.
Eddington Boulevard (Phase 3 - westbound) Farnborough to Windrift
New pavement is open to traffic.
Backfilling behind curb with dirt.
Eddington Boulevard (Phase 4 - eastbound) Farnborough to Windrift
Open the new pavement to traffic.
Pour driveway approaches.
Backfilling behind curb with dirt.
Flanders Drive (Phase 1 & 2)
New pavement is open to traffic.
Sugar Pine Road (Phase 1, 2, & 3) Walton to Black Maple
New pavement is open to traffic.
Sugar Pine Road (Phase 4) Walton to Black Maple
Complete paving the northbound lane.
Waiting for cure time on the new pavement.
Prepare concrete drive approaches.
Sanctuary Blvd at South Blvd
Complete.
Pheasant Ring/Eagle Drive (Phase 1)
New pavement is open to traffic.
Pheasant Ring/Eagle Drive (Phase 2)
Open to traffic.
Pour driveway approaches.
Pheasant Ring/Eagle Drive (Phase 3) - House 2979 to 2931
Remove pavement and earth excavation.
Install edge drain and aggregate base.
Cedar Shake/Lakewood Drive (Phase 1)
New pavement is open to traffic.
Cedar Shake/Lakewood Drive (Phase 2)
Open to Traffic.
Pour concrete driveway approaches.
Cedar Shake/Lakewood Drive (Phase 3)
Begin removing pavement and earth excavation.
Independence Drive/Court (Phase 1)
Install edge drain and aggregate base.
Begin paving.
Sidewalk Replacement Program
Removals are scheduled to start the week of August 12th
Check out our video update for this week!
Construction Update
on Jul 28, 2025
+
For the week of July 28th, 2025Eddington Boulevard (Phase 1 & 2) Farnborough to Windrift
New pavement is open to traffic.
Eddington Boulevard (Phase 3 - westbound) Farnborough to Windrift
New pavement is open to traffic.
Eddington Boulevard (Phase 4 - eastbound) Farnborough to Windrift
Complete paving.
Waiting for cure time on new pavement.
Flanders Drive (Phase 1 & 2)
New pavement is open to traffic.
Sugar Pine Road (Phase 1, 2, & 3) Walton to Black Maple
New pavement is open to traffic.
Sugar Pine Road (Phase 4) Walton to Black Maple
Paving northbound lane.
Sanctuary Blvd at South Blvd
Complete.
Pheasant Ring/Eagle Drive (Phase 1)
New pavement is open to traffic
Pheasant Ring/Eagle Drive (Phase 2)
Open to traffic.
Pheasant Ring/Eagle Drive (Phase 3)
Begin removing pavement.
Cedar Shake/Lakewood Drive (Phase 1)
New pavement is open to traffic.
Prepare driveway approaches.
Cedar Shake/Lakewood Drive (Phase 2)
Open to Traffic.
Prepare driveway approaches.
Independence Drive/Court
Removing pavement and earth excavation.
Installing edgedrain and aggregate base.
Sidewalk Replacement Program
Removals are scheduled to start the week of August 12th
Check out our video update for this week!
Construction Update
on Jul 18, 2025
+
For the week of July 21st, 2025Eddington Boulevard (Phase 1 & 2) Farnborough to Windrift
New pavement is open to traffic.
Flanders Drive (Phase 1 & 2)
New pavement is open to traffic.
Sugar Pine Road (Phase 1 & 2) Walton to Black Maple
New pavement is open to traffic.
Sugar Pine Road (Phase 3) Black Maple to Tanglewood
New pavement is open to traffic.
Pour concrete driveway approaches.
Sugar Pine Road (Phase 4) Black Maple to Tanglewood
Begin pavement removal and earth excavation.
Begin installing edge drain and placing aggregate base.
Sanctuary Blvd at South Blvd
Complete.
Pheasant Ring/Eagle Drive (Phase 1)
New pavement is open to traffic
Pheasant Ring/Eagle Drive (Phase 2)
Waiting for concrete cure time
Cedar Shake/Lakewood Drive (Phase 1)
New pavement is open to traffic.
Cedar Shake/Lakewood Drive (Phase 2)
Complete paving.
Independence Drive/Court (Phase 1)
Removing pavement and earth excavation
Sidewalk replacement Program
Work to be announced.
Residents: Please be mindful of your neighbors and refrain from parking your vehicle in areas that obstruct driveways and mailboxes.Applying curing compound over new concrete pavement on Westbound Pheasant Ring DriveInstalling form boards along proposed curb line on westbound Cedar Shake.Placing sand over the top of the recently placed edge drain pipe before compacting this backfill on Lakewood Drive.
Construction Update
on Jul 11, 2025
+
For the Week of July 14thEddington Boulevard (Phase 1 & 2) Farnborough to Windrift -
The new pavement is open to traffic.
Eddington Boulevard (Phase 3-westbound) West of Farnborough / Windrift to Essex -
The new pavement is open to traffic.
Eddington Boulevard (Phase 4-westbound) West of Farnborough / Windrift to Essex -
Begin removing pavement and earth excavation.
Flanders Drive (Phase 1 & 2) -
The new pavement is open to traffic.
Sugar Pine Road (Phases 1 & 2) Walton to Black Maple -
The new pavement is open to traffic.
Sugar Pine Road (Phase 3) Black Maple to Tanglewood -
The new pavement is open to traffic.
Pour concrete driveway approaches.
Pheasant Ring/Eagle Drive (Phase 1) -
The new pavement is open to traffic.
Pheasant Ring/Eagle Drive (Phase 2) -
Begin paving.
Cedar Shake/Lakewood Drive (Phase 1) -
The new pavement is open to traffic.
Pour concrete driveway approaches.
Cedar Shake/Lakewood Drive (Phase 2) -
Remove pavement and excavate earth.
Install edge drain and place aggregate base.
Possibly begin paving.
Sidewalk replacement Program -
Work to be announced.
Residents: Please be mindful of your neighbors and refrain from parking your vehicle in areas that obstruct mailboxes and driveways.
Construction Update
on Jul 03, 2025
+
For the Week of July 7thEddington Boulevard (Phase 1 & 2) Farnborough to Windrift -
Complete.
Eddington Boulevard (Phase 3-westbound) West of Farnborough / Windrift to Essex -
Paving is complete. Allow cure time.
Flanders Drive (Phase 1 & 2) -
Continue topsoil and hydro seed along the back of curb.
Sugar Pine Road (Phase 1) Walton to Black Maple -
Open to traffic.
Continue top soil and hydro seed.
Sugar Pine Road (Phase 2) Walton to Black Maple -
Open to Traffic.
Continue topsoil and hydro seed.
Sugar Pine Road (Phase 3) Black Maple to Tanglewood -
Complete earth excavation.
Complete installation of edge drain and aggregate base.
Complete form work and pave.
Pheasant Ring/Eagle Drive (Phase 1) -
Paving is complete.
Driveways waiting for cure time.
Pheasant Ring/Eagle Drive (Phase 2) -
Removing pavement and earth excavation.
Installing edge drain and placing aggregate base course.
Cedar Shake/Lakewood Drive (Phase 1) -
Open to traffic.
Preparing driveways for concrete.
Cedar Shake/Lakewood Drive (Phase 2) -
Begin removing pavement and earth excavation on Lakewood.
Sidewalk replacement Program -
Work to be announced.
Residents: Please be mindful of your neighbors and refrain from parking your vehicle in areas that obstruct mailboxes and driveways.
Pouring concrete on Cedar Shake Drive.
Machine grading the 21AA aggregate base on Eddington Boulevard.
Applying curing compound over the surface of concrete paving on Cedar Shake Drive.
Construction Update
on Jun 27, 2025
+
For the week of June 30th, 2025 No work will be performed on July 4th.Eddington Boulevard (Phase 1 and 2) Farnborough to Windrift
Complete
Eddington Boulevard (Phase 3) West of Farnborough / Windrift to Essex
Installing edge drain, placing aggregate and concrete forms.
Begin paving.
Flanders Drive (Phase 1 and 2)
Open to traffic.
Topsoil and hydroseed along the back of the curb.
Sugar Pine Road (Phase 1) Walton to Black Maple
Open to traffic.
Begin backfilling at the back of the curb.
Place topsoil and hydroseed.
Sugar Pine Road (Phase 2) Walton to Black Maple
Open to traffic.
Begin backfilling at the back of the curb.
Place topsoil and hydroseed.
Sugar Pine Road (Phase 3) Walton to Black Maple
Begin removing pavement.
Install edge drain and place aggregate base.
Sanctuary Blvd at South Blvd
Complete.
Pheasant Ring/Eagle Drive (Phase 1)
Paving is complete. Allow for cure time.
Begin forming driveway approaches.
Start Phase 2 demo.
Cedar Shake/Lakewood Drive (Phase 1)
Complete paving. Allow for cure time.
Begin forming driveway approaches.
Sidewalk replacement Program -
Work to be announced.
Residents: Please be mindful of your neighbors and refrain from parking your vehicle in areas that obstruct mailboxes and driveways.
Construction Update
on Jun 20, 2025
+
Eddington Boulevard (Phase 1) Farnborough to Windrift
Restoration along the back of curb.
Open to traffic mid week.
Eddington Boulevard (Phase 2) Farnborough to Windrift
Restoration along the back of curb.
Open to traffic mid week.
Eddington Boulevard (Phase 3) West of Farnborough / Windrift to Essex
Begin removing pavement and earth excavation.
Installing edge drain, aggregate and concrete forms.
Flanders Drive (Phase 1)
Open to traffic.
Topsoil and hydro seed along the back of curb.
Flanders Drive (Phase 2)
Complete paving at south end. Allow cure time for strength.
Pour concrete drive approaches. Allow cure time for strength.
Topsoil and hydro seed along the back of curb.
Sugar Pine Road (Phase 1) Walton to Black Maple
Open to traffic.
Begin backfilling at back of curb.
Sugar Pine Road (Phase 2) Walton to Black Maple
Paving is complete. Allowing cure time for strength.
Sanctuary Blvd at South Blvd
Will be opened this week.
Pheasant Ring/Eagle Drive (Phase 1)
Continue placing aggregate base and concrete forms.
Paving begins.
Cedar Shake/Lakewood Drive (Phase 1)
Continue removing pavement and earth excavation.
Continue installing edge drain.
Begin placing aggregate base.
Sidewalk replacement Program -
Removing miscellaneous sidewalk panels, prep and begin pouring concrete in the Rookery Woods subdivision.
Nearing the end of earth excavation for Phase 2 Sugar Pine at Black Maple Drive.
Construction Update
on Jun 13, 2025
+
For the week of June 16th, 2025Eddington Boulevard (Phase 1) Farnborough to Windrift
Open to construction traffic only.
Eddington Boulevard (Phase 2) Farnborough to Windrift
New pavement and driveway approaches have been completed.
Flanders Drive (Phase 1)
New pavement and driveway approaches have been compelted.
Flanders Drive (Phase 2)
Complete paving. Allow time for cure strength.
Sugar Pine Road (Phase 1) Walton to Black Maple
New pavement and driveway approaches have been completed.
Sugar Pine Road (Phase 2) Walton to Black Maple
Complete installation of edge drain.
Continue placing aggregate and concrete forms.
Paving.
Pheasant Ring/Eagle Drive (Phase 1)
Begin removing pavement and earth excavation.
Begin installing edge drain.
Begin placing aggregate base.
May begin paving at the end of the week.
Cedar Shake/Lakewood Drive (Phase 1)
Begin removing pavement and earth excavation.
Begin installing edge drain.
Begin placing aggregate base.
Sanctuary Blvd at South Blvd
Complete concrete on the west half of the boulevard.
Sidewalk Replacement Program
Begin removing miscellaneous sidewalk panels in the Rookery Woods subdivision.
Construction Update
on Jun 06, 2025
+
Eddington Boulevard (Phase 1) Farnborough to Windrift
Open to construction traffic only.
Eddington Boulevard (Phase 2) Farnborough to Windrift
Placing aggregate base and installing forms.
Pave the eastbound lane.
Flanders Drive (Phase 1)
New concrete driveways require cure time for strength.
Flanders Drive (Phase 2)
Continue pavement removal and earth excavation in the northbound lane.
Install edge drain and aggregate base in the northbound lane.
Begin paving the northbound lane if scheduling allows.
Sugar Pine Road (Phase 1) Walton to Black Maple
Begin placing driveway approaches along the east side of the street.
Sugar Pine Road (Phase 2) Walton to Black Maple
Begin removing west side of the boulevard.
Sanctuary Blvd at South Blvd
Place aggregate and pour concrete curb and gutter on the west half of the intersection.
Construction Update
on May 30, 2025
+
Eddington Boulevard (Phase 1) Farnborough to Windrift
Open to construction traffic only.
Eddington Boulevard (Phase 2) Farnborough to Windrift
Removing existing pavement and earth excavation.
Installing edge drain and placing aggregate base.
Flanders Drive (Phase 1)
New concrete requires cure time for strength.
Begin placing aggregate base for driveway approaches if required strengths are obtained on new pavement.
Flanders Drive (Phase 2)
Start pavement removal in the northbound lane if required strengths are obtained on new pavement.
Sugar Pine Road (Phase 1) Walton to Black Maple -
Continue placing aggregate base course.
Continue installing concrete forms.
Pave full width concrete in the northbound lanes.
Koala T Construction onsite placing 6" edge drain from east/northbound Sugar Pine Road.Koala T Construction onsite removing existing concrete pavement from west/southbound Flanders Drive. Existing subgrade removed to limits 14 inches below proposed pavement grade.
Construction Update
on May 23, 2025
+
During the Week of May 23rdEddington Boulevard (Phase 1) Farnborough to Windrift
Complete concrete paving in the westbound lane.
Cure time is required for the new concrete.
Eddington Boulevard (Phase 2) Farnborough to Windrift
Possibly begin removing pavement in the eastbound lane if required strength is obtained on new westbound concrete.
Flanders Drive (Phase 1)
Complete earth excavation in the southbound lane.
Complete edge drain installation and placing aggregate base in the southbound lane.
Begin placing forms and paving concrete in the southbound lane.
Sugar Pine Road (Phase 1) Walton to Black Maple
Begin pavement removal and earth excavation in the northbound lane.
Begin installing the edge drain along the east side of the street.
Begin placement of aggregate base in the northbound lane.
Construction Update
on May 16, 2025
+
During the Week of May 19thEddington Boulevard
Contractor will be installing edgedrain, placing aggregate base, and placing concrete forms in the westbound lane between Windrift and Farnsborough.
Flanders Drive
Begin removing pavement, earth excavation, installing edge drain, and placing aggregate base course in the southbound lane between Highsplint and Harlan Court.
Construction Updates Coming Soon
on May 06, 2025
+
Sign up HERE to receive updates on project progress, schedule changes, weather delays, detours, and other relevant information. Concrete replacement locations: Independence Dr/Ct, Cedar Shake Dr, Lakewood Dr, Sugar Pine Rd, Pheasant Ring Dr, Eagle Dr, Eddington Blvd, Sanctuary Blvd entrance, Flanders Dr, and Charlwood Dr.
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.