Latest Update
Final Update
Nov 18, 2022
Construction Completed
All the work has been completed! Some restoration areas will be evaluated in the spring and seed will be re-applied where growth is still needed.
We thank all the residents for their coordination and patience during the construction season.
See our 2022 Concrete Program Overview Video below!
Read More
Construction Updates
Final Update
on Nov 18, 2022
+
Construction Completed
All the work has been completed! Some restoration areas will be evaluated in the spring and seed will be re-applied where growth is still needed.
We thank all the residents for their coordination and patience during the construction season.
See our 2022 Concrete Program Overview Video below!
Project Update 11-11
on Nov 11, 2022
+
The streets listed below are open. Homeowners may reinstall irrigation. Restoration has been completed.
Greenleaf Dr
Rochdale Dr
Hillcrest Dr
Dunedin Dr
Intersection of Palm Aire and Dunedin
Cobride Ct and Dr
Quincy Dr
Highsplint Dr
Valley Stream Dr
Olympia Dr
Harlan Ct
Ivy Wood Ct
Whitney Dr
We thank you for your patience and cooperation during the construction season.
Project Update
on Nov 04, 2022
+
Construction Update
Week of November 7
The streets listed below are open. Homeowners may reinstall irrigation. Restoration has been completed. Please note that sawcutting and sealing for all streets will continue through the week of November 7.
Greenleaf Dr
Rochdale Dr
Hillcrest Dr
Dunedin Dr
Intersection of Palm Aire and Dunedin
Cobride Ct and Dr
Quincy Dr
Highsplint Dr
Valley Stream Dr
Olympia Dr
Harlan Ct
Restoration will be completed this week on the streets listed below:
Ivy Wood Ct
Whitney Dr
All schedules are weather dependent.
We thank you for your patience and cooperation during the construction season.
Project Update 10-28
on Oct 28, 2022
+
Construction Schedule
Please Note: For all streets, sawcutting and sealing will begin the week of October 31st. Depending on weather, this could take up to two weeks to complete.
Greenleaf Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Hillcrest Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Dunedin Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Intersection of Palm Aire and Dunedin
Week of October 31st – Intersection is open. Homeowners may reinstall irrigation. Restoration complete.
Cobridge Ct and Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Quincy Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed.
Highsplint Dr
Week of October 31st – Restoration will begin. Once the concrete is cured, the remaining driveways will be opened.
Valley Stream Dr
Week of October 31st – Entire entrance is open. Restoration complete.
Ivy Wood Ct
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin next week.
Whitney Dr
Week of October 31st – Street is open to traffic. Once the concrete is cured, the driveways will be opened. Restoration is expected to begin the week of November 7th.
Olympia Dr
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed next week.
Harlan Ct
Week of October 31st – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed next week.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 10-21
on Oct 21, 2022
+
Construction Schedule
Greenleaf Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Hillcrest Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Dunedin Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Intersection of Palm Aire and Dunedin
Week of October 24th – Intersection is open. Homeowners may reinstall irrigation. Restoration complete.
Cobridge Ct and Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Quincy Dr
Week of October 24th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed.
Highsplint Dr
Week of October 24th – Restoration will begin. Once the concrete is cured, the remaining driveways will be opened.
Valley Stream Dr
Week of October 24th – Entire entrance is open. Restoration complete.
Ivy Wood Ct
Week of October 24th – Street is open to traffic. Once the concrete is cured the driveways will be opened.
Whitney Dr
Week of October 24th – Street is open to traffic. Once the concrete is cured, the driveways will be opened.
Olympia Dr
Week of October 24th – Street and all driveways are open to traffic. Once the concrete is cured, the driveways will be opened. Restoration is complete.
Harlan Ct
Week of October 24th – Street is open to traffic. Once the concrete is cured, the driveways will be opened.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 10-14
on Oct 14, 2022
+
Construction Schedule
Greenleaf Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Hillcrest Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Dunedin Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Intersection of Palm Aire and Dunedin
Week of October 17th – Intersection is open. Homeowners may reinstall irrigation. Restoration complete.
Cobridge Ct and Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed.
Quincy Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin
Highsplint Dr
Week of October 17th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration may begin.
Valley Stream Dr
Week of October 17th – Entire entrance is open. Restoration complete.
Ivy Wood Ct
(One-way eastbound traffic will be maintained)
Week of October 17th – Complete concrete pour and wait for cure strength for westbound lane. Complete concrete pours for driveways.
Whitney Dr
Week of October 17th – Complete concrete pour and wait for cure strength for southbound lane. Complete concrete pours for driveways.
Olympia Dr
Week of October 17th – Cul-de-sac is open to traffic. Once the concrete is cured, the driveways will be opened. Restoration will begin.
Harlan Ct
Week of October 17th – Cul-de-sac is open to traffic. Driveways will be prepared and poured.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 10-7
on Oct 07, 2022
+
Construction Schedule
Greenleaf Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Hillcrest Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Dunedin Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Intersection of Palm Aire and Dunedin
Week of October 10th – Intersection is open. Homeowners may reinstall irrigation. Restoration complete.
Cobridge Ct and Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Quincy Dr
Week of October 10th – Both sides of the street and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin
Highsplint Dr
Week of October 10th – Waiting for concrete to cure to strength for northbound lane north of Dawson. All driveways are open for the southbound lane.
Valley Stream Dr
Week of October 10th – Entire entrance is open. Restoration complete.
Ivy Wood Ct
(One-way eastbound traffic will be maintained)
Week of October 10th – Complete concrete pour and wait for cure strength for westbound lane.
Whitney Dr
Week of October 10th – Open to traffic on the northbound lane. Driveways along the northbound lane are waiting for concrete to cure. Pour concrete for the southbound lane.
Olympia Dr
Week of October 10th – Cul-de-sac is open to traffic. Driveways will be prepared and poured.
Harlan Ct
Week of October 10th – Cul-de-sac is open to traffic. Driveways will be prepared and poured.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 9-30
on Sep 30, 2022
+
Construction Schedule
Greenleaf Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Hillcrest Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Dunedin Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Intersection of Palm Aire and Dunedin
Week of October 3rd – Intersection is open. Homeowners may reinstall irrigation. Restoration will begin.
Cobridge Ct and Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Quincy Dr
Week of October 3rd – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation.
Highsplint Dr
Week of October 3rd – Concrete pour for northbound lane north of Dawson. All driveways are open for the southbound lane.
Valley Stream Dr
Week of October 3rd – Entire entrance is open. Restoration complete.
Ivy Wood Ct
(One-way eastbound traffic will be maintained)
Week of October 3rd – Base preparation and concrete pour for the westbound lane.
Whitney Dr
Week of October 3rd – Open to traffic on the northbound lane. Begin demolition and pours of driveways along the northbound lane. Begin demolition and base preparation of the southbound lane.
Olympia Dr
Week of October 3rd – Waiting for concrete to attain strength.
Harlan Ct
Week of October 3rd – Concrete pour on the south half of the cul-de-sac. Waiting for concrete to attain strength.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 9-23
on Sep 23, 2022
+
Construction Schedule
Greenleaf Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration complete.
Rochdale Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will be complete.
Hillcrest Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Dunedin Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Intersection of Palm Aire and Dunedin
Week of September 26th – Concrete has been poured, waiting for cure strength.
Cobridge Ct and Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation.
Quincy Dr
Week of September 26th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation.
Highsplint Dr
Week of September 26th – Begin demolition and base preparation for the northbound lane north of Dawson. All driveways will be open on the southbound lane on Monday.
Valley Stream Dr
Week of September 26th – Entire entrance is open. Restoration complete.
Ivy Wood Ct
(One-way eastbound traffic will be maintained)
Week of September 26th – The eastbound lane and cul-de-sac will be opened.
Begin demolition and base preparation for the westbound lane.
Whitney Dr
Week of September 26th – Complete concrete pour of the northbound lane. Potentially begin demolition and base preparation of the southbound lane.
Olympia Dr
Week of September 26th – Begin concrete pour on the cul-de-sac.
Harlan Ct
Week of September 26th – Complete concrete paving of the cul-de-sac.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
Project Update 9-16
on Sep 16, 2022
+
Greenleaf Dr
Week of September 19th – Both sides of the street are open and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed next week as well.
Rochdale Dr
Week of September 19th – Both sides of the street are open and all driveways are open. Homeowners may reinstall irrigation. Restoration will be completed next week as well.
Hillcrest Dr
Week of September 19th – Both sides of the street are open and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Dunedin Dr
Week of September 19th – Both sides of the street are open and all driveways are open. Homeowners may reinstall irrigation. Restoration will begin.
Intersection of Palm Aire and Dunedin
September 22nd – Begin demolition and base preparation.
Cobridge Ct and Dr
Week of September 19th – Both sides of the street are open and all driveways are open. Homeowners may reinstall irrigation.
Quincy Dr
Week of September 19th – Both sides of the street are open and waiting for driveways to gain strength. Homeowners may reinstall irrigation.
Highsplint Dr
Week of September 19th – Both sides of the street are open south of Dawson. Driveways on the southbound side will be poured.
Valley Stream Dr
Week of September 19th – Entire entrance is open. Restoration will be completed next week as well.
Ivy Wood Ct
(One-way westbound traffic will be maintained)
Week of September 19th – Complete concrete paving for eastbound lane and cul-de-sac and wait for cure strength to be achieved.
Whitney Dr
Week of September 19th – Complete demolition, base preparation, and concrete pour of the northbound lane.
Olympia Dr
Week of September 19th – Begin demolition and base preparation of the cul-de-sac.
Harlan Ct
September 22nd – Begin demolition and base preparation of the cul-de-sac.
Project Update 9-9
on Sep 09, 2022
+
Greenleaf Dr
Week of September 12th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation.
Rochdale Dr
Week of September 12th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation.
Hillcrest Dr
Week of September 12th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation.
Dunedin Dr
Week of September 12th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation.
Intersection of Palm Aire and Dunedin
Week of September 12th – No Work
Cobridge Ct and Dr
Week of September 12th – Both sides of the streets and all driveways are open. Homeowners may reinstall irrigation.
Quincy Dr
(One-way southbound traffic will be maintained)
Week of September 12th – Complete concrete placement on the driveways. Once the concrete is cured, the street and driveways will be open.
Highsplint Dr
(One-way northbound traffic will be maintained)
Week of September 12th – Complete concrete placement on the southbound lane; concrete cure time.
Valley Stream Dr
Week of September 12th – Entire entrance is open.
Ivy Wood Ct
(One-way westbound traffic will be maintained)
Week of September 12th – Continue base preparation of eastbound lane and cul-de-sac.
Whitney Dr
Week of September 12th – Begin demolition and base preparation of the northbound lane.
Olympia Dr
September 15th – Begin demolition and base preparation of the cul-de-sac.
Harlan Ct
September 19th – Begin demolition and base preparation of the cul-de-sac.
Project Update 9-2
on Sep 02, 2022
+
Construction Schedule
No work will be performed on Monday, September 5th, Labor Day Holiday.
Greenleaf Dr
Week of September 6th – Both sides of the street and driveways are open.
Hillcrest Dr
Week of September 6th – Both sides of the street and driveways will be open.
Dunedin Dr
Week of September 6th – Both sides of the street and driveways are open.
Intersection of Palm Aire and Dunedin
Week of September 6th – No Work
Cobridge Ct and Dr
(One-way northbound traffic will be maintained)
Week of September 6th – Concrete cure time on the northbound lane.
Quincy Dr
(One-way southbound traffic will be maintained)
Week of September 6th – Concrete placement on the northbound lane. Once cure strength is achieved for the northbound lane, the driveways will be removed and replaced.
Rochdale Dr
Week of September 6th – Both sides of the streets are open. Concrete cure time for driveways.
Highsplint Dr
(One-way northbound traffic will be maintained)
Week of September 6th – Continue demolition and base preparation on the southbound lane from Lockport to Warrington.
Valley Stream Dr
(Closed)
Week of September 6th – Concrete cure time for the entire intersection.
Ivy Wood Ct
(One-way westbound traffic will be maintained)
Week of September 6th – Begin demolition and base preparation of eastbound lane and cul-de-sac.
Whitney Dr
Week of September 6th – No work. September 12th – Begin demolition and base preparation of northbound lane.
Other streets in the program will be updated as the schedule is determined.
All schedules are weather dependent.
We thank you for your patience and cooperation during the construction season.
Project Update 8-26
on Aug 26, 2022
+
Construction Schedule
Greenleaf Dr
(Two-way traffic will be maintained)
Week of August 29 –Both sides of the street will be open Monday.
Hillcrest Dr
(Two-way traffic will be maintained)
Week of August 29 – Waiting for concrete to cure for the northbound lane from Devonwood to Plesant View.
Dunedin Dr
(Two-way traffic will be maintained)
Week of August 29 – Waiting for concrete to cure on driveways before opening driveways for use.
Cobridge Ct and Dr
(One-way northbound traffic will be maintained)
Week of August 29 – Pour concrete for northbound lane.
Quincy Dr
(One-way southbound traffic will be maintained)
Week of August 29 – Complete base preparation, concrete forms, and pour concrete for northbound lane.
Rochdale Dr
(Two-way traffic will be maintained)
Week of August 29 – Both sides of the street open Monday. Driveways to be poured next week as well.
Highsplint Dr
(One-way southbound traffic will be maintained)
Week of August 29th – Demolition and base preparation southbound lane from Lockport to Warrington.
Valley Stream Dr
(Closed)
Week of August 29th – Pouring of concrete for entire intersection.
Ivy Wood Ct
(One-way westbound traffic will be maintained)
Week of August 29th – No work. September 6th begin demolition and base preparation of eastbound lane and cul-de-sac.
Other streets in the program will be updated as the schedule is determined. All schedules are weather dependent. We thank you for your cooperation during the construction process.
Project Update 8-19
on Aug 19, 2022
+
Construction Schedule
Greenleaf Dr
(Two-way traffic will be maintained)
Week of August 22 – Concrete placement on the eastbound lane east of Rochdale Drive.
Hillcrest Dr
(Two-way traffic will be maintained)
Week of August 22 – Concrete placement on northbound lane north of Devonwood Drive.
Dunedin Dr
(Two-way traffic will be maintained)
Week of August 22 – Backfilling behind the west curb. Preparing driveways for new concrete.
Cobridge Ct and Dr
(One-way southbound traffic will be maintained)
Week of August 22 – Preparing the northbound lane for concrete. Begin concrete placement on the northbound lane.
Quincy Dr
(One-way southbound traffic will be maintained)
Week of August 22 – Begin demolition on the northbound lane. Switch one-way traffic to the southbound lane.
Rochdale Dr
(Two-way traffic will be maintained)
Week of August 22 – Concrete placement on the northbound lane, south of Greenleaf Drive.
Highsplint Dr
(One-way southbound traffic will be maintained)
Week of August 22 – Preparing driveways for concrete.
Project Update 8-12
on Aug 12, 2022
+
Construction Schedule
Greenleaf Dr
(Two-way traffic will be maintained)
Week of August 15 – Complete base preparation and concrete forms for eastbound Greenleaf at Rochdale intersection, as well as northbound Rochdale, south of Greenleaf.
Hillcrest Dr
(Two-way traffic will be maintained)
Week of August 15 – Begin demolition on Monday on the northbound lane from Devonwood to Pleasant View.
Dunedin Dr
(Two-way traffic will be maintained)
Week of August 15 – Waiting for concrete to cure on the southbound lane. Expected to place concrete in driveways on the southbound lane. Waiting for concrete to cure on driveways on the northbound lane.
Cobridge Ct and Dr
(One-way northbound traffic will be maintained)
Week of August 15 – Begin demolition on the northbound lane.
Quincy Dr
(One-way southbound traffic will be maintained)
Week of August 15 – Waiting for concrete to cure in driveways on the southbound lane.
Rochdale Dr
(Two-way traffic will be maintained)
Week of August 15 – Complete base preparation and concrete forms on the northbound Rochdale, south of Greenleaf.
Highsplint Dr
(One-way southbound traffic will be maintained)
Week of August 15 – Complete base preparation, concrete forms, and place concrete on the northbound lane from Warington to Dawson.
Project Update 8-5
on Aug 05, 2022
+
Construction Schedule
Greenleaf Dr
(Two-way traffic will be maintained)
Week of August 8 – Waiting for the concrete to cure on eastbound Greenleaf and southbound Rochdale.
Hillcrest Dr
(Two-way traffic will be maintained)
Week of August 8 – Complete concrete placement on southbound lane and wait for concrete to cure.
Dunedin Dr
(Two-way traffic will be maintained)
Week of August 8 – Complete base preparation, edge drain, and concrete forms.
Cobridge Ct and Dr
(One-way northbound traffic will be maintained)
Week of August 8 – Complete concrete placemen for the intersection of court and drive and wait for concrete to cure.
Quincy Dr
(One-way southbound traffic will be maintained)
Week of August 8 – Potential demolition of the northbound lane.
Rochdale Dr
(Two-way traffic will be maintained)
Week of August 8 – Waiting for the concrete cure on southbound lane
Highsplint Dr
(One-way southbound traffic will be maintained)
Week of August 8 – Continued demolition of the northbound lane from Warington to Dawson.
Project Update 8-2
on Aug 02, 2022
+
Project Update 7-29
on Jul 29, 2022
+
Construction Schedule
Greenleaf Drive
(Two-way traffic maintained)
Week of August 1 – Concrete placement on the eastbound/southbound lane.
Hillcrest Drive
(One-way northbound traffic maintained)
Week of August 1 – Finish demolition, edge drain installation, aggregate, forms and concrete placement on southbound lane.
Dunedin Drive
(Two-way traffic maintained)
Week of August 1 – Begin demolition on southbound lane and sump line discharge pipe installation.
Cobridge Ct and Drive
(One-way northbound traffic will be maintained)
Week of August 1 – Concrete placement on a small section of the intersection.
Quincy Dr
(One-way northbound traffic will be maintained)
Week of August 1 – Concrete cure time.
Rochdale Dr
(Two-way traffic maintained)
Week of August 1 – Concrete placement on the southbound lane.
All other locations will be updated as soon as the schedule is determined. All schedules are weather dependent. We thank you for your cooperation during the construction process.
Project Update 7-22
on Jul 22, 2022
+
Construction Schedule
Greenleaf Drive
(Two-way traffic maintained)
Week of July 25 – Demolition of the westbound lane at the east corner of Greenleaf and begin demolition of the southbound lane of Rochdale.
Hillcrest Drive
(Two-way traffic maintained)
Week of July 25 – Demolition of the southbound lane from Pleasant View to the south corner of Hillcrest.
Dunedin Drive
(Two-way traffic maintained)
Week of July 25 – Concrete is curing.
Cobridge Ct and Drive
(One-way northbound traffic will be maintained)
Week of July 25 – Complete concrete pour for cul-de-sac.
Quincy Dr
(One-way northbound traffic will be maintained)
Week of July 25 – Finish demolition, base preparation, edge drain, concrete forms, and concrete pour for the southbound lane.
Rochdale Dr
(Two-way traffic maintained)
Week of July 25 – Demolition of the southbound lane begins.
All other locations will be updated as soon as the schedule is determined. All schedules are weather dependent. We thank you for your cooperation during the construction process.
Project Update 7-15
on Jul 15, 2022
+
Construction Schedule
Greenleaf Drive
(Two-way traffic maintained)
Week of July 18 – Pour concrete for northbound and westbound lanes.
Hillcrest Drive
(Two-way traffic maintained)
Week of July 18 – Base preparation, edge drain, and concrete forms for the northbound lane from Hillcrest Dr corner north to Devonwood to begin.
Dunedin Drive
(Two-way traffic maintained)
Week of July 18 – Base preparation and edge drain installation.
Cobridge Ct and Drive
(Two-way traffic will be maintained)
Week of July 18 – Demolition of cul-de-sac and southbound lane to continue.
Quincy Dr
July 19 – Zoom meeting will be held
July 21 – Demolition to begin (anticipated)
Rochdale Dr
(Two-way traffic maintained)
August 1 (tentative) – Demolition for the southbound lane begins.
All other locations will be updated as soon as the schedule is determined. All schedules are weather dependent. We thank you for your cooperation during the construction process.
Project Update 7-8
on Jul 08, 2022
+
Construction Schedulev
Greenleaf Drive
(Two-way traffic maintained)
Week of July 11 – Base preparation, edge drain, and concrete forms for the west westbound lane.
Hillcrest Drive
(Two-way traffic maintained)
Week of July 11 – Demolition of northbound lane from Hillcrest Dr corner north to Devonwood begins
Dunedin Drive
June 11 – Zoom meeting for residents will be held
July 13 – Demolition begins (anticipated)
Cobridge Ct and Drive
June 12 – Zoom meeting for residents will be held
July 15 – Demolition begins (anticipated)
Rochdale Dr
(Two-way traffic maintained)
July 18 or 25 (tentative) – Demolition for the southbound lane begins
All other locations will be updated as soon as the schedule is determined. All schedules are weather dependent. We thank you for your cooperation during the construction process.
Project Update 7-1
on Jul 01, 2022
+
Construction Schedule
Greenleaf Drive
(Two-way traffic maintained)
July 5-10 – Demolition of westbound lane begins
Hillcrest Drive
(Two-way traffic maintained)
July 11-17 – Demolition of northbound lane from Hillcrest Dr corner north to Devonwood begins
Dunedin Drive
June 11 – Zoom meeting for residents will be held
July 13 – Demolition begins (anticipated)
Cobridge Ct and Drive
June 12 – Zoom meeting for residents will be held
July 15 – Demolition begins (anticipated)
Rochdale Dr
(Two-way traffic maintained)
July 18 or 25 (tentative) – Demolition for the southbound lane begins
All other locations will be updated as soon as the schedule is determined. All schedules are weather dependent. We thank you for your cooperation during the construction process.
Project Update 6-24
on Jun 24, 2022
+
Construction Schedule
The contractor plans to begin concrete road construction on Wednesday, July 6th. The contractor intends to start on Greenleaf Dr. Below is the anticipated order of streets to be constructed:
Greenleaf Dr.
Rochdale Dr
Valley stream Dr
Hillcrest Dr
Dunedin Dr
Cobridge Dr
Cobridge Ct
Quincy Dr
Streets within the scope of the project not mentioned above will be added at a later date. The exact dates for each street have not yet been determined. Residents will receive notices for Zoom meetings prior to the start of construction. Details and specific questions will be addressed at the Zoom meeting. We thank you for your cooperation during the construction process.
Project Information
on May 27, 2022
+
The City of Rochester Hills has awarded a contract to Koala-T Construction to perform concrete road replacement within your subdivision. Work is tentatively scheduled to start in the Valley Stream Subdivision on the first week of July. Typically, it takes approximately 6 to 8 weeks to complete both sides of the road and driveways. Please note the extent of selective driveway repairs is only within the City's right-of-way (ROW), which is typically 16 feet from the back of curb.
Weekly Constant Contact updates will be sent to any resident who signs up regarding status of where the contractor is working and where they will proceed next.
Scope of work includes:
•Remove and replace the existing 8-inch concrete over the 6-inch aggregate base.
•Install 6-inch edge drain under the back of curb where applicable.
•Selective replacement of driveways up to the ROW line.
•A typical replacement takes about 4 weeks per each half side of the road.
Spalding DeDecker (SDA) is the City's consultant providing full-time inspection and construction engineering services.
Frequently Asked Questions
Will sprinklers and other items located within the right-of-way be affected?
The public road ROW typically extends 16½ feet from the back of curb. The contractor's paving operations will generally impact an area of 3 feet from back of curb. If you are within the limits of the proposed replacement work and have sprinkler heads/lines within 3 feet of the back of curb, we ask that you excavate the lines and pull back the sprinkler heads/lines out of the construction influence area. In addition, we ask that you turn off sprinklers so as to keep the construction area clear of water and maintaining quality of road replacement. Once the road construction is completed and the area behind the back of curb has been backfilled you may reinstall your sprinkler lines and heads before the topsoil and seed are placed. Any sprinkler head/lines that are not temporarily relocated by the homeowner and are damaged will not be repaired by the City or contractor. Other landscape items such as decorative rocks, plantings, etc. should also be relocated to 3 feet from the back of curb. In the case of decorative brick paver driveways, the contractor will remove the bricks and stack them neatly outside of the construction area. Homeowners will be responsible for resetting the brick pavers. For specific locations of work, please be on the lookout for paint mark-ups identifying the limits of the repair work.
Will mail delivery be affected?
Mail service will continue throughout the duration of the project, with minimal delays and minor disruptions. Temporary mailboxes will be grouped at a single location on either end of the repair area so residents and USPS can easily access them. The contractor will make efforts to pave around decorative brick mailboxes. If your brick mailbox is removed it will not be reinstalled by the contractor. New mailboxes must conform to USPS standards. Please reference www.usps.com/manage/mailboxes.htm for standards.
Will trash pick-up be impacted?
Minimal disruption may occur to disposal services. Please locate your trash and recycle bins on the side of road open to traffic to help accommodate pick-up during construction. Please label house address on trash and recycle bins to help keep track of bins. You may want to coordinate with your neighbor on the opposite side of the street to set trash and recycle bins next to theirs. We will also be working with the contractor to help in moving trash and recycle bins if needed. Please call with any concerns or accommodations you may need.
Will there be road closures/where should we park?
Local access will be maintained throughout the duration of the project. While the Intent is to have one lane of traffic open at all times and no scheduled road closures, there may be certain operations that require the temporary closure of the roadway. The Rochester Hills Fire Department will be notified of any such closures and the contractor will have the road open to at least one lane of traffic by the end of the workday. Please park vehicles at least 20 feet away from the construction barrels at both ends of the project limits so the contractor has adequate access to the construction area. Other typical parking options, while the road is under construction on your half of the street, is to coordinate parking your vehicle in the neighboring driveway across the street or on an adjacent street that is not being worked on.
Will bus stop locations be effected?
The City will review and coordinate the bus stop locations with the schools and minimize conflicts. The stops will be maintained at all times during the school year.
Private work?
The Contractor and Subcontractor shall NOT perform any private work within the project area until the work under this Contract is completed unless written approval is received from the City of Rochester Hills.
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.
Grady Rollins - Construction Inspector
Spalding DeDecker