Latest Update
Construction Update
Oct 05, 2020
The 2020 Concrete Road Program project is nearly completed! The last of the concrete will be poured today. The driveways shown below will be open by Monday, October 12.
Avon Ravines #2
October 5 - Concrete placement on driveway approaches (Woodridge Ct)
Stratford Knolls
October 5 - Concrete placement on driveway approaches (Chalet Dr)
The construction crew has started removing traffic control devices, clean out bags, and other miscellaneous items. The crew will remain on site performing restoration, joint sealing, clean up, and other punch list items, including mailbox repairs, cracked concrete repairs, etc.
On behalf of the construction team, we want to thank everyone for their cooperation and patience during this project.
Read More
Construction Updates
Construction Update
on Oct 05, 2020
+
The 2020 Concrete Road Program project is nearly completed! The last of the concrete will be poured today. The driveways shown below will be open by Monday, October 12.
Avon Ravines #2
October 5 - Concrete placement on driveway approaches (Woodridge Ct)
Stratford Knolls
October 5 - Concrete placement on driveway approaches (Chalet Dr)
The construction crew has started removing traffic control devices, clean out bags, and other miscellaneous items. The crew will remain on site performing restoration, joint sealing, clean up, and other punch list items, including mailbox repairs, cracked concrete repairs, etc.
On behalf of the construction team, we want to thank everyone for their cooperation and patience during this project.
Construction Update
on Sep 15, 2020
+
Construction continues in the following subdivisions:
• Wildflower (Primrose Dr)
• Covington Place (Brunswick, Waverly Dr)
• Cumberland Hills (Poco Ct)
• Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
• Meadowbrook Valley (Box Canyon Ct)
• Stratford Knolls (Canterbury Trail Dr, Chalet Dr)
Primrose Drive (Two-way traffic will be maintained)
September 16 - Concrete curing at Primrose and Goldenrod intersection and crossover between the islands
Covington Place
September 10 to September 17 - Concrete cure time
Poco Court
September 11 to September 17 - Concrete cure time
Avon Ravines #2
September 9 to September 16 - Concrete cure time
Box Canyon Court
September 14 - Concrete removal on northbound lane
September 14 to September 15 - Stone placement, concrete forming, and edge drain installation
September 16 to September 18 - Concrete placement
September 18 to September 25 - Concrete cure time
Stratford Knolls (One-way traffic will be maintained north and east on Chalet Dr and on southbound Canterbury Trail Dr during Phase 2; see traffic plan)
September 16 - Concrete placement on driveway approaches (phase 2)
September 15 to September 18 - Concrete removal (phase 3)
September 18 to September 21 - Stone placement, concrete forming, and edge drain installation
September 22 to September 25 - Concrete placement
Construction Update
on Sep 08, 2020
+
NOTE: Due to the rain over the holiday weekend, construction work has been slightly delayed.
Construction continues in the following subdivisions:
• Wildflower (Primrose Dr)
• Covington Place (Brunswick, Waverly Dr)
• Cumberland Hills (Poco Ct)
• Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
• Meadowbrook Valley (Box Canyon Ct)
• Stratford Knolls (Canterbury Trail Dr, Chalet Dr)
Primrose Drive (Two-way traffic will be maintained)
September 9 - Concrete placement at the Primrose and Goldenrod intersection and crossover between the islands
September 9 to September 16 - Concrete cure time
Covington Place
September 10 - Concrete placement on westbound Brunswick
September 10 to September 17 - Concrete cure time
Poco Court
September 11 - Concrete placement on the westbound side
September 11 to September 18 - Concrete cure time
Avon Ravines #2
September 9 - Concrete placement on Woodridge Ct
September 9 to September 16 - Concrete cure time
Box Canyon Court
September 10 to September 11 - Concrete removal on north bound lane
Stratford Knolls (One-way traffic will be maintained north and east on Chalet Dr and on southbound Canterbury Trail Dr during Phase 2; see traffic plan)
September 3 to September 10 - Concrete cure time (phase 2)
September 14 to September 17 - Concrete removal (phase 3)
Construction Update
on Aug 31, 2020
+
NOTE: Due to the heavy rain last week, construction work has been slightly delayed.
Construction continues in the following subdivisions:
Wildflower (Primrose Dr)
Covington Place (Brunswick, Waverly Dr)
Cumberland Hills (Poco Ct)
Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
Meadowbrook Valley (Box Canyon Ct)
Stratford Knolls (Canterbury Trail Dr, Chalet Dr)
Primrose Drive(Two-way traffic will be maintained)
August 31 to September 2 - Concrete cure time
September 2 - Concrete removal at Primrose and Goldenrod intersection
Covington Place
September 2 - Concrete removal on westbound Brunswick
September 3 - Base preparation, edge drain, concrete form placement
September 10 - Concrete placement on westbound Brunswick
Poco Court
September 3 to September 4 - Concrete removal on the westbound side
September 4 to September 5 - Base preparation, edge drain, concrete form placement
Avon Ravines #2
August 31 to September 1 - Concrete removal (phase 3)
September 1 to September 2 - Base preparation, edge drain, concrete form placement
September 2 - Concrete placement on driveway approaches
September 8 to September 9 - Concrete placement (phase 3)
Box Canyon Court
August 31 to September 1 - Concrete placement on southbound side
September 1 to September 8 - Concrete cure time
Stratford Knolls (One-way traffic will be maintained north and east on Chalet Dr and on southbound Canterbury Trail Dr during Phase 2; see traffic plan)
August 31 - Base preparation, edge drain, concrete form placement
September 1 to September 4 - Concrete placement (phase 3)
September 4 to September 11 - Concrete cure time (phase 3
Construction Update
on Aug 24, 2020
+
NOTE: Traffic plan shift in Stratford Knolls. Starting August 24, one-way traffic will be maintained on south bound Canterbury Trail Dr and one-way traffic on east bound Chalet Dr.
Construction continues in the following subdivisions:
• Wildflower (Primrose Dr)
• Covington Place (Brunswick, Waverly Dr)
• Cumberland Hills (Poco Ct)
• Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
• Meadowbrook Valley (Box Canyon Ct)
• Stratford Knolls (Canterbury Trail Dr, Chalet Dr)
Primrose Drive (Two-way traffic will be maintained)
August 24 to August 28 - Concrete cure time
August 28 - Concrete placement in driveway approaches
Covington Place
August 24 - Concrete placement on Waverly and Brunswick
August 25 to August 28 - Concrete cure time
Poco Court
August 25 - Concrete placement on the south side of Poco Ct
August 26 to August 31 - Concrete cure time
Avon Ravines #2
August 24 to August 28 - Concrete cure time
August 28 - Concrete placement in driveway approaches
Box Canyon Court
August 24 to August 25 - Base preparation, edge drain, concrete form placement
August 26 to August 27 - Concrete placement on southbound lane
August 28 to September 3 - Concrete cure time
Stratford Knolls (One-way traffic will be maintained north and east on Chalet Dr and on southbound Canterbury Trail Dr during Phase 2)
August 24 to August 26 - Concrete removal starting on the north end of the project limit on Canterbury Trail Drive and working south and turning east on Chalet Drive
August 27 to August 28 - Base preparation, edge drain, concrete form placement

Construction Update
on Aug 17, 2020
+
Construction this week will take place in the following subdivisions:
Wildflower (Primrose Dr)
Covington Place (Brunswick, Waverly Dr)
Cumberland Hills (Poco Ct)
Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
Meadowbrook Valley (Box Canyon Ct)
Stratford Knolls (Canterbury Trail Dr, Chalet Dr)
Primrose Drive (Two-way traffic will be maintained)
August 17 to August 19 - Concrete placement on the main road.
Covington Place
August 17 - Pavement removal on Waverly and Brunswick.
Poco Court
August 18 - Pavement removal on the south side of Poco Court.
Avon Ravines #2
August 20 to August 21 - Concrete placement on the southbound portion of Woodridge Dr.
Box Canyon Court
August 19 to August 21 - Pavement removal on the west side on Box Canyon Court.
Stratford Knolls (One-way traffic will be maintained north and east on Chalet Dr and on northbound Canterbury Trail Dr during Phase 1)
August 20 to August 21 - Concrete placement on the driveways.
Construction Update
on Aug 10, 2020
+
Construction this week will take place in the following subdivisions:
• Wildflower (Primrose Dr)
• Covington Place (Brunswick, Waverly Dr)
• Cumberland Hills (Poco Ct)
• Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
• Meadowbrook Valley (Box Canyon Ct)
• Stratford Knolls (Canterbury Trail Dr, Chalet Dr)
Primrose Drive (Two-way traffic will be maintained)
August 10 to August 11 - Pavement removal on the southbound lane.
August 12 to August 14 - Concrete placement on the main road.
Covington Place
No work planned for this week.
Poco Court
No work planned for this week.
Avon Ravines #2
August 12 to August 14 - Pavement removal begins at 7 a.m., Wednesday on the southbound portion of Woodridge Dr.
Box Canyon Court
No work planned for this week.
Stratford Knolls (One-way traffic will be maintained north and east on Chalet Dr and on northbound Canterbury Trail Dr during Phase 1)
August 10 to August 11 - Concrete placement on the main road.
Construction Update
on Aug 03, 2020
+
Construction this week will take place in the following subdivisions:
• Wildflower (Primrose Dr)
• Covington Place (Brunswick, Waverly Dr)
• Cumberland Hills (Poco Ct)
• Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
• Meadowbrook Valley (Box Canyon Ct)
• Stratford Knolls (Canterbury Trail Dr, Chalet Dr)
Primrose Drive (Two-way traffic will be maintained)
August 4 - Pavement removal on the southbound lane due to begin in the afternoon. Please move vehicles out of driveways prior to construction. Further notification will be forthcoming.
Covington Place
Driveways on Brunswick and Waverly will be open this week once we get satisfactory compression strength test results on the concrete.
Poco Court
No work planned for this week.
Avon Ravines #2
August 6 to August 7 - Driveways to be poured in both cul-de-sacs.
Box Canyon Court (Work will be done in the cul-de-sac only this week)
August 3 to August 4 - Edge drain will be placed. Concrete placement has been delayed because the underlying base was found to be soft and pumping. Additional work is being done to strengthen the base.
August 5 to August 6 - Concrete placement in the cul-de-sac.
Stratford Knolls (One-way traffic will be maintained north and east on Chalet Dr and on northbound Canterbury Trail Dr during Phase 1)
August 3 to August 4 - Demolition continues on Chalet Dr.
August 5 to August 7 - Stone base placement and edge drain installation.
Construction Update
on Jul 27, 2020
+
Construction this week will take place in the following subdivisions:
•Wildflower (Primrose Dr)
•Covington Place (Brunswick, Waverly Dr)
•Cumberland Hills (Poco Ct)
•Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
•Meadowbrook Valley (Box Canyon Ct)
•Stratford Knolls (Canterbury Trail Dr, Chalet Dr)
Primrose Drive(Two-way traffic will be maintained)
July 27 - Driveway approaches poured on the northbound side
July 28 to July 31 - Concrete cure time
Covington Place
July 27 to August 3 - Brunswick cul-de-sac and Waverly Dr cure time
July 29 - Driveway approaches poured in cul-de-sac and on Waverly Dr
Poco Court (Work will be done in the cul-de-sac only this week)
July 29 - Driveway approaches poured in cul-de-sac
July 30 to August 3 - Concrete cure time
Avon Ravines #2
July 27 - Prep work on Woodbridge Dr
July 27 to July 28 - Concrete placement in Woodbridge Ct cul-de-sac
July 28 to July 29 - Concrete placement in Woodbridge Dr cul-de-sac
July 29 to August 5 - Concrete cure time
Box Canyon Court(Work will be done in the cul-de-sac only this week)
July 28 - Demolition in the cul-de-sac only
July 31 - Concrete placement in the cul-de-sac
Stratford Knolls (One-way traffic will be maintained north and east on Chalet Dr and on northbound Canterbury Trail Dr. during Phase 1)
July 29 - Demolition stars at the north property line of 224 Canterbury Trail Dr and working south.
NOTE: Residents at 224, 236, and 248 Canterbury Trail should have vehicles moved out of the driveway by 7:00 a.m. Wednesday (7/29). Prepare to have no access for 2 to 3 weeks.
July 30 to July 31 - Demolition continues south on Canterbury Trail and south on Chalet Dr. ending at the south property line of 2506 Chalet Dr.
Construction Update
on Jul 21, 2020
+
Construction this week will take place in the following subdivisions:
• Wildflower (Primrose Dr)
• Covington Place (Brunswick, Waverly Dr)
• Cumberland Hills (Poco Ct)
• Avon Ravines #2 (Woodridge Dr, Woodridge Ct)
Primrose Drive (Two-way traffic will be maintained)
July 20 - Final section of concrete poured on the northbound side
July 21 to July 27 - Concrete cure time
Covington Place
July 20 - Brunswick cul-de-sac demolition completion
July 21 - Waverly Drive demolition (Waverly will be closed in both directions)
July 23 to July 24 - Concrete placement on Brunswick and Waverly Drive
Note: Due to the size of the circle the Brunswick cul-de-sac, the concrete must be poured in 4 sections with cure time in between placement.
Poco Court
(Work will be done in the cul-de-sac only this week)
July 21 to July 22 - Concrete placement
July 23 to July 27 - Concrete cure time
Avon Ravines #2
July 22 - Demolition in the Woodridge Drive cul-de-sac
July 23 - Demolition in the Woodridge Court cul-de-sac
July 27 to July 28 - Concrete placement in the cul-de-sacs
July 29 to August 3 - Concrete cure time
Construction Update
on Jun 30, 2020
+
All phases of construction have been completed on the following:
• Old Homestead Drive and Merriweather Lane
• Parkwood Drive
• Cherrywood Court
• Rosewood Lane
There may be miscellaneous restoration and cleanup at all above locations. Construction is currently paused and will resume on July 8. The subdivisions affected will be named in the next update, along with an updated construction schedule.
We thank the residents for their patience and cooperation during all stages of construction.
Construction Update
on Jun 16, 2020
+
Construction continues at 4 locations: 1) Old Homestead and Merriweather Lane, 2) Parkwood Drive, 3) Cherrywood Court, 4) Rosewood Lane. Below is an updated construction schedule:
Old Homestead Drive and Merriweather Lane (Two-way traffic will be maintained)
Phase 1 - Completed
Phase 2 - Completed
Phase 3
June 15 to June 22 - Concrete cure time
Parkwood Drive (One-way traffic eastbound beginning May 12)
Phase 1
June 12 to June 19 - Concrete cure time
Cherrywood Court (Closed to all traffic beginning May 20)
Phase 1
June 8 - Concrete placement
June 15 - Concrete placement in the approach
Rosewood Lane (Two-way traffic will be maintained)
June 16 - Concrete placement
June 17 to June 24 - Concrete cure time
Over the next two weeks, there will be miscellaneous restoration and cleanup at all above locations.
Construction Update
on Jun 08, 2020
+
Construction continues at 4 locations: 1) Old Homestead and Merriweather Lane, 2) Parkwood Drive, 3) Cherrywood Court, 4) Rosewood Lane. Below is an updated construction schedule:
Old Homestead Drive and Merriweather Lane (Two-way traffic will be maintained)
Phase 1 - COMPLETED
Phase 2 - COMPLETED
Phase 3
June 8 - Demolition
June 9 - Placing stone, edge drain, grading, and forming
June 15 - Concrete placement
June 15 to June 22 - Concrete cure time
Parkwood Drive (One-way traffic eastbound beginning May 12)
Phase 1 - COMPLETED
Phase 2
June 8 - Final Preparation
June 9 to June 12 - Concrete placement
June 12 to June 19 - Concrete cure time
Cherrywood Court (Closed to all traffic beginning May 20)
Phase 1
June 8 - Concrete placement
June 15 - Concrete placement in the approach
Rosewood Lane (Two-way traffic will be maintained)
June 8 to June 12 - Concrete cure time
Construction Update
on Jun 01, 2020
+
Construction continued last week after the Memorial Day break. Concrete placement on Parkwood Dr. was completed on the north side. Once that pavement cures, the driveways will be poured. Concrete placement will be taking place this week on Old Homestead Dr, Cherrywood Ct, and Rosewood Lane. Below is an updated construction schedule:
Old Homestead Drive and Merriweather Lane (Two-way traffic will be maintained)
Phase 1 - COMPLETED
Phase 2
June 2 - Concrete Placement
June 2 to June 8 - Concrete cure time
Phase 3
June 8 - Demolition
June 8 to June 10 - Placing stone, edge drain, grading, and forming
June 11 - Concrete placement
June 11 to June 18 - Concrete cure time
June 19 - Driveways
Parkwood Drive (One-way traffic eastbound beginning May 12)
Phase 1
June 1 to June 4 - Concrete cure time
June 5 - Driveways
Phase 2
June 8 - Demolition
Cherrywood Court (Closed to all traffic beginning May 20)
Phase 1
June 1 to June 3 - Concrete placement
June 3 to June 10 - Concrete cure time
June 11 - Driveways
Rosewood Lane (Two-way traffic will be maintained)
Phase 1
June 1 to June 3 - Concrete placement
June 3 to June 10 - Concrete Cure time
June 11 - Driveways
Construction Update
on May 26, 2020
+
The contractor was able to complete a full week of construction, despite the rain last week. However, the contractor ran into logistical limitations, as they attempted to prepare Parkwood on one end and pour concrete on the other. As a result, the crew had to delay the concrete pour a few days to allow for traffic to be maintained on the south side of the road. Below is an updated construction schedule:
Old Homestead Drive and Merriweather Lane (Two-way traffic will be maintained)
Phase 1 - COMPLETED
Phase 2
May 26 - Demolition
May 27 to May 28 - Placing stone, edge drain, grading, and forming
May 29 - Concrete Placement
May 30 to June 6 - Concrete cure time
Parkwood Drive (One-way traffic eastbound beginning May 12)
Phase 1
May 26 to May 28 - Concrete placement
May 28 to June 4 - Concrete cure time
Cherrywood Court (Closed to all traffic beginning May 20)
Phase 1
May 26 to May 29 - Placing stone, edge drain, grading, and forming
June 1 to June 3 - Concrete placement
June 3 to June 10 - Concrete cure time
Construction Update
on May 18, 2020
+
Construction of the Concrete Road Program began on May 11, starting at the Old Homestead and Merriweather intersection and along Parkwood Dr. Rain on May 14 and 15, along with the weather forecast for the week starting May 18, has already impacted the schedule. Below is an updated construction schedule:
Old Homestead Drive and Merriweather Lane (Two-way traffic will be maintained)
Phase 1
May 19 - Concrete placement
May 19 to May 26 - Concrete cure time
Parkwood Drive
(One-way traffic eastbound beginning May 12)
Phase 1
May 18 to May 20 - Demolition begins on the west end
May 18 to May 21 - Placing stone, edge drain, grading, and forming
May 19 to May 22 - Concrete placement
May 22 to May 29 - Concrete cure time
Cherrywood Court
(Closed to all traffic beginning May 20)
Phase 1
May 20 to May 22 - Demolition begins on the west end
May 20 to May 22 - Placing stone, edge drain, grading, and forming
May 26 to May 28 - Concrete placement
May 28 to June 4 - Concrete cure time
Construction Begins Today
on May 11, 2020
+
Construction starts May 11, 2020 on Old Homestead & Merriweather Intersection, and Parkwood Rd. See construction milestones below.
Old Homestead Drive and Merriweather Lane (Two-way traffic will be maintained)
Phase 1
May 11 - Demolition begins
May 12 - Placing stone and edge drain
May 13 - Forming and grading
May 14 - Concrete placement
May 15 to May 21 - Cure time
Parkwood Drive (One-way traffic eastbound beginning May 12)
Phase 1
May 12 to May 19 - Demolition begins on the west end
May 13 to May 19 - Placing stone, edge drain, grading and forming
May 15 to May 20 - Concrete placement
May 21 to May 28 - Cure time
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.
CLARK FRENCH - PROJECT MANAGER
SPALDING DEDECKER
(248) 844-6286
CFRENCH@SDA-ENG.COM