Latest Update
Construction Update
Oct 11, 2024
All Areas
The contractor is scheduled to complete the remaining paving items today (October 11).
All remaining punch list items including ditch restoration will take place over the next few weeks.
Read More
Construction Updates
Construction Update
on Oct 11, 2024
+
Construction Update
on Oct 04, 2024
+
Areas A and B
The contractor is scheduled to be in the area over the next few weeks to place seed and mulch in areas of need.
Areas C and D
The contractor will be on-site in the next two weeks to finish culvert placement and paving the remaining approaches. Most areas have been restored with seed and fertilizer. Please continue to irrigate these areas for best growth.
Construction Update
on Sep 27, 2024
+
Areas A and B
The contractor is scheduled to be in the area over the next week to place seed and mulch in areas of need.
Areas C and D
The contractor will be on-site in the next two weeks to finish culver placement and paving the remaining approaches. Most areas have been restored with seed and fertilizer. Please continue to irrigate these areas for best growth.
Check out the Program Overview Video Below!
Construction Update
on Sep 20, 2024
+
Areas A and B
The contractor is scheduled to be in the area over the next week to place seed and mulch in areas of need.
Areas C and D
The contractor is waiting for utilities to be marked on Mack so they can finish the culvert installation. All manholes have been adjusted and most areas have been restored. An aggregate shoulder still needs to be placed in a few areas along with three asphalt approaches.
Check out the Program Overview Video Below!
Paving Complete
on Sep 13, 2024
+
Paving has been completed in all areas. The contractor will continue to finish punch list items and continue to clean up in the coming weeks.
Check out the Program Overview Video Below!
Construction Update
on Sep 06, 2024
+
Area A and Area B:
The Contractor is contractually responsible for finishing all storm damaged locations and punch list items in areas A & B. Work should be completed in the near future.
Area C and Area D:
All roadway paving has been completed. The contractors still have to install culverts, replace driveways and shoulders, and complete the clean-up along the edges of the road. The contractor will be on-site over the next few weeks to finish the remaining outstanding work.
Construction Update
on Aug 30, 2024
+
Area A and Area B:
The Contractor is contractually responsible for finishing all storm damaged locations and punch list items in areas A & B. Work should be completed shortly after the Labor Day holiday.
Area C and Area D:
The cement stabilization of both areas C & D is complete. Final asphalt paving is scheduled for Wednesday 9/4/24. NOTE: Residents in these areas should move their vehicles by 7:00 am Wednesday (9/4).
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
Construction Update
on Aug 23, 2024
+
Area A and Area B:
The Contractor is contractually responsible for finishing all storm damaged locations and punch list items in areas A & B. Work should be completed shortly after the Labor Day holiday.
Area C and Area D:
The Contractor will begin cement stabilization on August 26th and August 27th. Work will start in Area C (Reynolds) and finish in Area D (Hickory Lane and Carlton). NOTE: Residents in these areas should move their vehicles by 7:00 am Monday (8/26) and Tuesday (8/27). The streets should reopen approximately 4 hours after the completion of each street. Final asphalt paving is scheduled for Tuesday, September 3rd.
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
Construction Update
on Aug 16, 2024
+
CONSTRUCTION UPDATE
Looking ahead to the week of August 18th:
Area A and B
The contractor will be in the area over the next two weeks, making all repairs and finishing any outstanding items that still need to be completed.
Area C and Area D
The contractor has completed pulverizing all roads in Areas C & D and will continue to grade these areas over the next week.
The cement stabilization of the roads in Areas C & D will begin on 8/26 and 8/27. More information will be available as the dates draw near.
Access to your residence will remain open, but you may incur small delays.
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
Construction Update
on Aug 09, 2024
+
CONSTRUCTION UPDATE
Area C and Area D
The Contractor will start the crushing and shaping of the asphalt on Monday, August 12th, which will take approximately one week. Soil stabilizing, fine grading, and paving will follow in the coming weeks. The construction process will take approximately four weeks.
AREA C
W REYNOLDS RD (W Lake Drive to Mack)
ROE ST (W Lake Drive to W Reynolds)
LEE ST (Ridge to W Reynolds)
MACK AVE (W Lake Drive to W Reynolds)
AREA D
CARLTON ST (E Lake Drive to Hickory Island)
HICKORY ISLAND ST (END to E Lake Dr)
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
Construction Updates
on Aug 02, 2024
+
Area C and Area D: Road work is currently schedule to begin on August 12. A more detailed scheduled will be provided next week.
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
Construction Update
on Jul 19, 2024
+
July 22 - July 26
Area A and Area B: All concrete work and drainage structures have been completed in both areas. Work will continue over the next 4 to 5 weeks to complete any minor repairs or defects.
Area C and Area D: Road work is currently scheduled to begin on August 12. Updates will be posted as the date draws nearer.
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
Construction Update
on Jul 12, 2024
+
July 15 - July 19
The contractor is scheduled to make all repairs from this past week’s storm, finish the concrete drive approaches, and begin raising all manholes in areas A and B.
Area C and Area D: Road work is currently scheduled to begin on July 22. Updates will be posted as the date draws nearer.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project.
Construction Update
on Jul 05, 2024
+
The contractor has finished restoration in Area A and continues restoration in Area B.
July 8 - July 13
All restoration in Area B should be completed by the end of next week (July 13).
Concrete driveways will have a minimum cure time of 3 days and may take 5 days.
Area C and Area D: Road work is currently scheduled to begin on July 22. Updates will be posted as the date draws nearer.
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
Construction Update
on Jun 28, 2024
+
The contractor continues to place shoulder gravel and topsoil in areas A and B.
July 1 - July 5
Areas A and B: The contractor will begin pouring concrete driveways and raising manhole castings in the streets next week.
Concrete driveways will have a minimum cure time of 3 days and may take 5 days.
No work will occur July 4-5 in observance of the Independence Day holiday.
Area C and Area D: Road work is currently scheduled to begin on July 22. Updates will be posted as the date draws nearer.
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
Construction Update
on Jun 21, 2024
+
All paving was completed in Area A and Area B.
June 24 - June 28
Area A: Restoration work will begin Monday 6/24/24 and will include completing drive approaches, gravel shoulders, and seeding.
Area B: Final restoration will take place after restoration is complete in area A.
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
Construction Update
on Jun 14, 2024
+
Area B: The contractor completed road grading, ditch clean out and culvert installations.
June 17 - June 21
Area A: The contractor is scheduled to complete the top course of asphalt on 6/19/24. Restoration work will begin the following week.
Area B: The contractor is scheduled to place the base course of asphalt on Monday 6/17/24.The contractor is scheduled to place the top course of asphalt on Wednesday 6/19/24 or Thursday 6/20/24.
Restoration will take place over the following two weeks
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
.
Construction Update
on Jun 07, 2024
+
Area A: The top course of asphalt and the project restoration should take place in approximately 2 weeks. Area B: All roads have been pulverized and are currently being reshaped.
June 10 - June 14
The contractor will complete the ditch clean out and culvert replacements as directed by the plans. Road grading and aggregate base compaction will continue throughout the week. A date has not been set for the first placement of asphalt.
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
Construction Update
on May 31, 2024
+
Area A: All culverts have been replaced and all ditches have been cleaned out. Final paving and restoration for Area A is to take place within the next two to three weeks.
June 3 - June 7
Area B: Pavement removal is scheduled to begin on Thursday (6/6/24). Road grading should begin immediately after. Residents will continue to have access to their driveways with occasional minimal delays.
The construction schedule is weather-dependent.
For questions, please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
Construction Update
on May 24, 2024
+
All of the aggregate base has been graded and compacted. The base course of asphalt has been placed for all streets in phase A. All mailboxes have been relocated as necessary. No work is expected on Monday, May 27 due to Memorial Day.
May 28 - May 31
The contractor is scheduled to replace culverts and clean out the specified ditches for Phase A. The contractor will start lowering structures in Area B starting on Thursday 5/30/24 & Friday 5/31/24.
The construction schedule is weather-dependent.
For questions please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
Construction Update
on May 17, 2024
+
CONSTRUCTION UPDATE
Pulverizing and drive approach removals will be completed for Gossard, Biber and Porter Avenue by the end of Friday, 5/17/24.
Aggregate base grading, ditch cleanout, and culvert installation will continue next week.
The construction schedule is weather-dependent.
For questions please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
Construction Notice
on May 06, 2024
+
CONSTRUCTION BEGINS NEXT WEEK
Weather dependent, the work in Area A is currently anticipated to start the week of May 13, 2024.
Tentative construction schedule for Area A:
May 13 - Mobilization, traffic control set up, drainage structure temp lowering.
May 14 - Pulverizing
May 15-25 - Removals, ditch cleanout, culvert work, machine grading
May 27-28 - HMA 13A leveling course
May 28-29 - HMA 36A wearing course
May 30-31 - Restoration and approach work
The construction schedule is weather-dependent.
For questions please contact Kelly Green, Project Inspector.
616.647.7902 | roads@meridian.mi.us
We are looking forward to working with you toward a successful construction project!
The streets listed below are to be resurfaced in 2024. This work is being done as part of the Meridian Township Local Roads Program, funded by the Township Local Roads Millage. The road resurfacing will generally consist of pulverizing/ grinding-up and re-grading the existing asphalt surface into a new gravel base (crushing & shaping), then repaving with new asphalt pavement. The construction is anticipated to proceed by Area, in the approximate order shown in the table below.
AREA A
BIBER ST (Gossard to Towar)
GOSSARD AVE (Biber to END)
PORTER AVE (Biber to END)
BIBER ST (Pollard to Hardy)
AREA B
SUNHOLLOW CT (Royal Oak to Sunhollow Ln)
SUNHOLLOW LN (Crest to Sunhollow Ct)
BAKER ST (Sunhollow Ct to Marsh Rd)
HIGH ST (Crest to Baker St)
MICHAEL ST (Marsh Rd to Marsh Rd)
AREA C
W REYNOLDS RD (W Lake Drive to Mack)
ROE ST (W Lake Drive to W Reynolds)
LEE ST (Ridge to W Reynolds)
MACK AVE (W Lake Drive to W Reynolds)
AREA D
CARLTON ST (E Lake Dr to Hickory Island)
HICKORY ISLAND ST (END to E Lake Dr)
We sincerely apologize in advance for any inconvenience caused by the construction, and we truly appreciate your patience and understanding while we work to improve your neighborhood and our entire community.
Coming Soon!
on Feb 29, 2024
+
Stay tuned for Construction Updates
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.