Latest Update
Construction Update
Area: Tacoma Hills, Tihart Road, and Newman Road
The contractor finished sidewalk grading, pulverized the asphalt surface from Marsh to Cornell, and installed new culverts under the proposed drive approaches in Tacoma Hills and on Newman Road.
COMING UP
Tihart Rd
Date TBD - Road base stabilization from Marsh to Cornell.
8/20 - 8/22 - Clean ditches and place the concrete sidewalks.
Newman Rd
8/18 - Pulverize Newman from Van Atta to Meridian.
Tacoma Hills
Waiting for cooler temperatures and an end to the drought before restoring the ditches.
Date TBD - Adjust drainage structures in the road.
This schedule is dependent on weather conditions. The schedule will change every time it rains on a scheduled work day.
Construction Updates
Construction Update
Area: Tacoma Hills, Tihart Road, and Newman Road
The contractor finished sidewalk grading, pulverized the asphalt surface from Marsh to Cornell, and installed new culverts under the proposed drive approaches in Tacoma Hills and on Newman Road.
COMING UP
Tihart Rd
Date TBD - Road base stabilization from Marsh to Cornell.
8/20 - 8/22 - Clean ditches and place the concrete sidewalks.
Newman Rd
8/18 - Pulverize Newman from Van Atta to Meridian.
Tacoma Hills
Waiting for cooler temperatures and an end to the drought before restoring the ditches.
Date TBD - Adjust drainage structures in the road.
This schedule is dependent on weather conditions. The schedule will change every time it rains on a scheduled work day.
Construction Update
CONSTRUCTION SCHEDULE
Tacoma Hills, Tihart Road, and Newman Rd
The contractors have placed gravel shoulders on Tacoma Hills. On Tihart and Newman Roads, the contractor finished removing stumps, removed sidewalk and curb at Twinning Dr and Powel Rd, and performed saw cutting for pavement removal.
COMING UP
Tihart Rd
8/11 - 8/12 - Pulverize the asphalt surface from Marsh Road to Cornell Road.
8/13 - 8/15 - Culvert installations and ditch grading.
Place concrete curb and sidewalk.
8/18 - 8/19 - Road base stabilization from Marsh to Cornell.
8/22 or 8/23 - Place the first layer of asphalt.
Newman Rd
8/12 - 8/15 - culvert installations and ditch grading.
Date TBD - Pulverize the asphalt surface from Van Atta to Meridian.
Tacoma Hills
Finish placing the gravel shoulders
8/18 - 8/22 - If necessary, mailboxes will be adjusted to meet the USPS’ current specifications.
This schedule is dependent on weather conditions. The schedule will change every time it rains on a scheduled work day.
Video Update Coming Soon!
Construction Update
Tacoma Hills and Tihart Road
Beginning Monday, August 4th, the contractor will:
Tacoma Hills
Finish grading ditches and begin to restore disturbed areas with seed fertilizer and mulch.
Mailboxes will be adjusted as required.
Manholes will be raised on both the curb and non-curb construction projects.
Placing and grading the gravel shoulders.
Tihart
Begin removing stumps.
Excavate ditches.
Install culverts.
This schedule is dependent on weather conditions.
Construction Update
Tacoma Hills
A look ahead to the week ending Saturday, August 2:
Now that all paving is complete in Tacoma Hills, our contractors will begin restoring ditches and doing project cleanup over the next few weeks. Mailboxes will be adjusted as required. Manholes will be raised on both the curb and non-curb construction projects.
We ask all residents in the newly paved areas of Tacoma Hills not to schedule any work that would require heavy equipment on the new paved surface for a week. The surface needs time to cool properly.
Construction Update
Tacoma Hills
A look ahead to the week ending Saturday, July 26th:
Saturday, July 19th:
Asphalt drives will be placed on Pawnee Circle. Please keep cars off the new drive for two hours (let the pavement cool).
Final paving is scheduled for Wednesday or Thursday (7/23 or 7/24) of next week and should be completed by Friday (7/25). Ditch cleanout and slope restoration will be completed after the final asphalt has been placed.
This schedule is dependent on weather conditions.
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
- For roads that do NOT have curb and gutter, the Township’s contractor continues to work on any necessary ditch cleanout and culvert replacement work.
- All ditch roads have had the existing asphalt crushed with the exception of Tacoma Blvd. Tacoma Blvd will likely be crushed the week of June 9 once the other roads have been paved.
- The Township’s contractor will be completing the final milling (i.e. removing existing asphalt) from roads that have curb and gutter on May 30.
- The milling and crushing work typically moves past a given driveway in approximately 10 minutes, after which there is a rough gravel surface that you can drive on. The milling, crushing and paving work will be completed one lane at a time, thus the streets will be usable on at least one side at almost all times. An entire street is normally milled in one (1) day. Once the milling is finished, the first layer of new asphalt will be placed within 10 days.
- Weather dependent, the Township’s contractor will be paving roads on May 31 and June 2-6. The roads with curb and gutter are likely to be paved first.
- Additional paving dates will be announced when they are scheduled.
- Saturday may 31st. the contractor may pave Yuma Trail in the late afternoon time permitting.
- Monday June 2nd the contractor will pave Yuma Trail if not completed on Saturday and will finish paving the remaining streets.
- June 3rd – June 6th the contractor will work on ditch clean out and culvert restoration.
Construction Update
Tacoma Hills Update #3
- All storm sewer spot repairs have been completed.
- All curb and gutter spot repairs have been completed.
- For roads that do NOT have curb and gutter, the Township’s contractor continues to work on any necessary ditch clean out and culvert replacement work.
- Weather dependent, the Township’s contractor will be lowering manholes on curb and gutter roads on May 22 and 23.
- Weather dependent, the Township’s contractor is scheduled to crush the existing asphalt in place on roads that do NOT have curb and gutter.
- Weather dependent, the Township’s contractor will be milling (i.e. removing existing asphalt) from roads that have curb and gutter on May 29 and 30.
- The milling and crushing work typically moves past a given driveway in approximately 10 minutes, after which there is a rough gravel surface that you can drive on. The milling, crushing and paving work will be completed one lane at a time, thus the streets will be usable on at least one side at almost all times. An entire street is normally milled in one (1) day. Once the milling is finished, the first layer of new asphalt will be placed within 10 days.
- Weather dependent, the Township’s contractor will be paving roads from June 2-6. The roads with curb and gutter are likely to be paved first.
- Additional paving dates will be announced when they are scheduled.
Tacom Hills Update #2
Tacoma Hills Update
Consumers Energy Work
Construction Updates Coming Soon
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.