Latest Update
Construction Update
Tacoma Hills
A look ahead to the week ending Saturday July 19th
Saturday July 12th:Concrete driveways will be placed on Tacoma Blvd. Please keep vehicles off the new driveways until the contractor opens them up. Driveways should be open in three days.
Ditch clean out and slope restoration will take place throughout next week.
The paving scheduled for July 15th through the 17th has been delayed and will take place in two weeks. We are sorry for the delay but the shipment of rubber additive for the asphalt has been delayed at the Canadian border. This material is a necessity for the asphalt mix that we are placing.
The schedule is dependant on weather conditions.
Construction Updates
Construction Update
Tacoma Hills
A look ahead to the week ending Saturday July 19th
Saturday July 12th:Concrete driveways will be placed on Tacoma Blvd. Please keep vehicles off the new driveways until the contractor opens them up. Driveways should be open in three days.
Ditch clean out and slope restoration will take place throughout next week.
The paving scheduled for July 15th through the 17th has been delayed and will take place in two weeks. We are sorry for the delay but the shipment of rubber additive for the asphalt has been delayed at the Canadian border. This material is a necessity for the asphalt mix that we are placing.
The schedule is dependant on weather conditions.
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
Construction Update
- For roads that do NOT have curb and gutter, the Township’s contractor continues to work on any necessary ditch cleanout and culvert replacement work.
- All ditch roads have had the existing asphalt crushed with the exception of Tacoma Blvd. Tacoma Blvd will likely be crushed the week of June 9 once the other roads have been paved.
- The Township’s contractor will be completing the final milling (i.e. removing existing asphalt) from roads that have curb and gutter on May 30.
- The milling and crushing work typically moves past a given driveway in approximately 10 minutes, after which there is a rough gravel surface that you can drive on. The milling, crushing and paving work will be completed one lane at a time, thus the streets will be usable on at least one side at almost all times. An entire street is normally milled in one (1) day. Once the milling is finished, the first layer of new asphalt will be placed within 10 days.
- Weather dependent, the Township’s contractor will be paving roads on May 31 and June 2-6. The roads with curb and gutter are likely to be paved first.
- Additional paving dates will be announced when they are scheduled.
- Saturday may 31st. the contractor may pave Yuma Trail in the late afternoon time permitting.
- Monday June 2nd the contractor will pave Yuma Trail if not completed on Saturday and will finish paving the remaining streets.
- June 3rd – June 6th the contractor will work on ditch clean out and culvert restoration.
Construction Update
Tacoma Hills Update #3
- All storm sewer spot repairs have been completed.
- All curb and gutter spot repairs have been completed.
- For roads that do NOT have curb and gutter, the Township’s contractor continues to work on any necessary ditch clean out and culvert replacement work.
- Weather dependent, the Township’s contractor will be lowering manholes on curb and gutter roads on May 22 and 23.
- Weather dependent, the Township’s contractor is scheduled to crush the existing asphalt in place on roads that do NOT have curb and gutter.
- Weather dependent, the Township’s contractor will be milling (i.e. removing existing asphalt) from roads that have curb and gutter on May 29 and 30.
- The milling and crushing work typically moves past a given driveway in approximately 10 minutes, after which there is a rough gravel surface that you can drive on. The milling, crushing and paving work will be completed one lane at a time, thus the streets will be usable on at least one side at almost all times. An entire street is normally milled in one (1) day. Once the milling is finished, the first layer of new asphalt will be placed within 10 days.
- Weather dependent, the Township’s contractor will be paving roads from June 2-6. The roads with curb and gutter are likely to be paved first.
- Additional paving dates will be announced when they are scheduled.
Tacom Hills Update #2
Tacoma Hills Update
Consumers Energy Work
Construction Updates Coming Soon
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.