Latest Update
Construction Update
CONSTRUCTION SCHEDULE
Updated Road Construction Schedule for Roads without Curb & Gutter in Tacoma Hills and Upcoming Closures to Tacoma Blvd
Ongoing Construction Activity: For roads that do NOT have curb and gutter, the Township’s contractor continues to work on driveway restoration.
June 18-19: Weather permitting, new curb and gutter will be poured at the Tacoma Blvd and Hamilton Road intersection.
June 20: Weather permitting, Tacoma Blvd, from Tomahawk Road to Hamilton Road, will receive a cement stabilization treatment to add additional strength under Tacoma Blvd prior to paving. Tacoma Blvd, from Tomahawk Road to Hamilton Road, will be closed to traffic until sometime on Tuesday, June 24 to perform this treatment and allow it to properly cure. To protect Tacoma Blvd and to help us ensure the new road realizes its full life expectancy, please do NOT go around the barricades until they are removed by the contractor.
June 23: Weather permitting, the Township’s contractor will perform an asphalt stabilization treatment to the gravel base of Tacoma Blvd, from 4369 Tacoma Blvd to Hamilton Road, to add additional strength under Tacoma Blvd prior to paving.
We will have to close Tacoma Blvd, from 4369 Tacoma Blvd to Hamilton Road, beginning around 7 a.m. on Monday, June 23 until sometime on Tuesday, June 24 to perform this treatment and allow it to properly cure.
Therefore, if your driveway connects to Tacoma Blvd where closures are shown on the map, please move your vehicle to an adjacent road by the evening of Sunday, June 22. THIS INCLUDES THE DRIVEWAYS AT 1940 PAWNEE TRL AND 4578, 4556, AND 4530 TACOMA BLVD.
Please continue to park your vehicles on adjacent roads until the barricades are removed by the construction crew sometime on Tuesday, June 24. During this period of time, all motorists in Tacoma Hills will have to use Manitou Dr to get in and out of the neighborhood, as shown on the map below.
To protect Tacoma Blvd and to help us ensure the new road realizes its full life expectancy, please do NOT go around the barricades.
Paving dates will be announced soon for paving the first layer of asphalt on Pawnee Cir, the east-most portion of Lagoon Drive, and Tacoma Blvd (from 4369 Tacoma Blvd to Hamilton Road).
Then, once all roads without curb and gutter have had the first layer of asphalt paved, the second and final layer of asphalt will be paved on these roads over the course of about 3 days.
Once all paving work has been completed, manholes will then be raised and have cement collars poured around them. Cones will be left around the concrete collars while the concrete cures.
Please do NOT drive over the concrete collars around manholes under the cones have been collected.
If the weather cooperates, the Township currently anticipates being able to at least have the first layer of asphalt paved on all of the roads before July 4th holiday. The contractors will likely need return after the 4th of July holiday to finish paving, raise manholes, and finish final restoration work.
We sincerely apologize in advance for any inconvenience caused during construction, and we truly appreciate your patience and understanding while we work to improve your neighborhood and our entire community.
Construction Updates
Construction Update
CONSTRUCTION SCHEDULE
Updated Road Construction Schedule for Roads without Curb & Gutter in Tacoma Hills and Upcoming Closures to Tacoma Blvd
Ongoing Construction Activity: For roads that do NOT have curb and gutter, the Township’s contractor continues to work on driveway restoration.
June 18-19: Weather permitting, new curb and gutter will be poured at the Tacoma Blvd and Hamilton Road intersection.
June 20: Weather permitting, Tacoma Blvd, from Tomahawk Road to Hamilton Road, will receive a cement stabilization treatment to add additional strength under Tacoma Blvd prior to paving. Tacoma Blvd, from Tomahawk Road to Hamilton Road, will be closed to traffic until sometime on Tuesday, June 24 to perform this treatment and allow it to properly cure. To protect Tacoma Blvd and to help us ensure the new road realizes its full life expectancy, please do NOT go around the barricades until they are removed by the contractor.
June 23: Weather permitting, the Township’s contractor will perform an asphalt stabilization treatment to the gravel base of Tacoma Blvd, from 4369 Tacoma Blvd to Hamilton Road, to add additional strength under Tacoma Blvd prior to paving.
We will have to close Tacoma Blvd, from 4369 Tacoma Blvd to Hamilton Road, beginning around 7 a.m. on Monday, June 23 until sometime on Tuesday, June 24 to perform this treatment and allow it to properly cure.
Therefore, if your driveway connects to Tacoma Blvd where closures are shown on the map, please move your vehicle to an adjacent road by the evening of Sunday, June 22. THIS INCLUDES THE DRIVEWAYS AT 1940 PAWNEE TRL AND 4578, 4556, AND 4530 TACOMA BLVD.
Please continue to park your vehicles on adjacent roads until the barricades are removed by the construction crew sometime on Tuesday, June 24. During this period of time, all motorists in Tacoma Hills will have to use Manitou Dr to get in and out of the neighborhood, as shown on the map below.
To protect Tacoma Blvd and to help us ensure the new road realizes its full life expectancy, please do NOT go around the barricades.
Paving dates will be announced soon for paving the first layer of asphalt on Pawnee Cir, the east-most portion of Lagoon Drive, and Tacoma Blvd (from 4369 Tacoma Blvd to Hamilton Road).
Then, once all roads without curb and gutter have had the first layer of asphalt paved, the second and final layer of asphalt will be paved on these roads over the course of about 3 days.
Once all paving work has been completed, manholes will then be raised and have cement collars poured around them. Cones will be left around the concrete collars while the concrete cures.
Please do NOT drive over the concrete collars around manholes under the cones have been collected.
If the weather cooperates, the Township currently anticipates being able to at least have the first layer of asphalt paved on all of the roads before July 4th holiday. The contractors will likely need return after the 4th of July holiday to finish paving, raise manholes, and finish final restoration work.
We sincerely apologize in advance for any inconvenience caused during construction, and we truly appreciate your patience and understanding while we work to improve your neighborhood and our entire community.
Construction Update
CONSTRUCTION SCHEDULE (UPDATED*)
Updated Road Construction Schedule for Roads without Curb & Gutter in Tacoma Hills and Upcoming Closures to Tacoma Blvd
Ongoing Construction Activity: For roads that do NOT have curb and gutter, the Township’s contractor continues to work on driveway restoration.
Monday, June 16: Weather permitting, Pawnee Cir, the east-most portion of Lagoon Drive, and Tacoma Blvd (from 4369 Tacoma Blvd to Hamilton Road) will have the existing asphalt crushed in place. Manholes will be lowered after the existing asphalt has been crushed.
The crushing work typically moves past a driveway in approximately 10 minutes, after which there is a rough gravel surface that you can drive on. The milling, crushing, and paving work will be completed one lane at a time. Thus, the streets will be usable on at least one side at almost all times. Once the crushing is finished, the first layer of new asphalt will be paved within 10 days.
The Township’s contractor will also work on grading and shaping the crushed asphalt and gravel on Pawnee Cir, the east-most portion of Lagoon Drive, and Tacoma Blvd (from 4369 Tacoma Blvd to Hamilton Road).
*Thursday, June 19: Weather permitting, the Township’s contractor will perform an asphalt stabilization treatment to the gravel base of Tacoma Blvd (from 4369 Tacoma Blvd to Hamilton Road) to add additional strength under Tacoma Blvd prior to paving.
We will have to close Tacoma Blvd beginning around 7 a.m. on Thursday, *June 19 until around 11 a.m. on Friday, June 20 to perform this treatment and allow it to properly cure.
If your driveway connects to Tacoma Blvd where closures are shown on the map below, please move your vehicle to an adjacent road by Sunday evening. Please continue to park your vehicles on adjacent roads until the barricades are removed by the construction crew on Wednesday, June 18. During this period of time, all motorists in Tacoma Hills will have to use Manitou Dr to get in and out of the neighborhood.
To protect Tacoma Blvd and to help us ensure the new roads realize their full life expectancy, please do NOT go around the barricades.
Paving dates will be announced later this week for paving the first layer of asphalt on Pawnee Cir, the east-most portion of Lagoon Drive, and Tacoma Blvd (from 4369 Tacoma Blvd to Hamilton Road).
Once all roads without curb and gutter have had the first layer of asphalt paved, the second and final layer of asphalt will be paved on these roads over the course of about 3 days.
Once all paving work has been completed, manholes will then be raised and have cement collars poured around them. Cones will be left around the concrete collars while the concrete cures.
Please do NOT drive over the concrete collars around manholes under the cones have been collected.
Weather permitting, the Township currently anticipates being able to complete all work prior to the July 4th holiday.
This schedule is dependent on weather conditions. More updates will be provided next week. We appreciate your patience and cooperation during this project.
Construction Update
CONSTRUCTION SCHEDULE
Updated Road Construction Schedule for Roads without Curb & Gutter in Tacoma Hills and Upcoming Closures to Tacoma Blvd
Ongoing Construction Activity: For roads that do NOT have curb and gutter, the Township’s contractor continues to work on driveway restoration.
Friday, June 13: New curb and gutter will be poured at the Tacoma Blvd and Hamilton Road intersection.
Monday, June 16: Weather permitting, Pawnee Cir, the east-most portion of Lagoon Drive, and Tacoma Blvd (from 4369 Tacoma Blvd to Hamilton Road) will have the existing asphalt crushed in place. Manholes will be lowered after the existing asphalt has been crushed.
The crushing work typically moves past a driveway in approximately 10 minutes, after which there is a rough gravel surface that you can drive on. The milling, crushing, and paving work will be completed one lane at a time. Thus, the streets will be usable on at least one side at almost all times. Once the crushing is finished, the first layer of new asphalt will be paved within 10 days.
The Township’s contractor will also work on grading and shaping the crushed asphalt and gravel on Pawnee Cir, the east-most portion of Lagoon Drive, and Tacoma Blvd (from 4369 Tacoma Blvd to Hamilton Road).
Tuesday, June 17: Weather permitting, the Township’s contractor will perform an asphalt stabilization treatment to the gravel base of Tacoma Blvd (from 4369 Tacoma Blvd to Hamilton Road) to add additional strength under Tacoma Blvd prior to paving.
We will have to close Tacoma Blvd beginning around 7 a.m. on Tuesday, June 17 until around 11 a.m. on Wednesday, June 18 to perform this treatment and allow it to properly cure.
If your driveway connects to Tacoma Blvd where closures are shown on the map below, please move your vehicle to an adjacent road by Sunday evening. Please continue to park your vehicles on adjacent roads until the barricades are removed by the construction crew on Wednesday, June 18. During this period of time, all motorists in Tacoma Hills will have to use Manitou Dr to get in and out of the neighborhood.
To protect Tacoma Blvd and to help us ensure the new roads realize their full life expectancy, please do NOT go around the barricades.
Paving dates will be announced later this week for paving the first layer of asphalt on Pawnee Cir, the east-most portion of Lagoon Drive, and Tacoma Blvd (from 4369 Tacoma Blvd to Hamilton Road).
Once all roads without curb and gutter have had the first layer of asphalt paved, the second and final layer of asphalt will be paved on these roads over the course of about 3 days.
Once all paving work has been completed, manholes will then be raised and have cement collars poured around them. Cones will be left around the concrete collars while the concrete cures.
Please do NOT drive over the concrete collars around manholes under the cones have been collected.
Weather permitting, the Township currently anticipates being able to complete all work prior to the July 4th holiday.
This schedule is dependent on weather conditions. More updates will be provided next week. We appreciate your patience and cooperation during this project.
Construction Update
Tacoma Hills
June 9th / 12th - The contractor will be grading ditches, clearing spoils from the shoulders, and replacing concrete driveways.
June 13th or 14th - Tacoma Blvd and Pawnee Cr. are scheduled to be pulverized. Driveway access will be maintained; however, delays should be expected. No date has been set for final paving.
This schedule is dependent on weather conditions. More updates will be provided next week. We appreciate your patience and cooperation during this project.
Construction Update
Tacoma Hills
- For roads that do NOT have curb and gutter, the Township’s contractor continues to work on any necessary ditch cleanout and culvert replacement work.
- All ditch roads have had the existing asphalt crushed with the exception of Tacoma Blvd. Tacoma Blvd will likely be crushed the week of June 9 once the other roads have been paved.
- The Township’s contractor will be completing the final milling (i.e. removing existing asphalt) from roads that have curb and gutter on May 30.
- The milling and crushing work typically moves past a given driveway in approximately 10 minutes, after which there is a rough gravel surface that you can drive on. The milling, crushing and paving work will be completed one lane at a time, thus the streets will be usable on at least one side at almost all times. An entire street is normally milled in one (1) day. Once the milling is finished, the first layer of new asphalt will be placed within 10 days.
- Weather dependent, the Township’s contractor will be paving roads on May 31 and June 2-6. The roads with curb and gutter are likely to be paved first.
- Additional paving dates will be announced when they are scheduled.
The schedule is dependant on weather conditions. More updates will be provided next week. We appreciate your patience and cooperation during this project.
Construction Update
Tacoma Hills
This week, the contractor has completed all driveway removals and culvert installations in the Tacoma Hills area except for Tacoma Blvd. This is scheduled for a later date. Mailboxes have been relocated, as needed, to allow for the construction of the new shoulder.
Coming Up
5/27 - The contractor will be grading the shoulders of all streets except for Tacoma Blvd. in preparation for aggregate shoulder placement.
5/28 - The contractor will be pulverizing all streets except for Tacoma Blvd. All streets will remain open with driveway access; some delays can be expected as the machine passes your driveway.
5/28-29 - The contractor will be fine-grading the pulverized streets.
6/2 - 6/6 - The contractor will be paving streets for both the Crush and Shape and Mill and Fill contracts in the Tacoma Hills area. The date for each street is to be determined. More updates will be provided next week.
Tacoma Hills Update #3
- All storm sewer spot repairs have been completed.
- All curb and gutter spot repairs have been completed.
- For roads that do NOT have curb and gutter, the Township’s contractor continues to work on any necessary ditch clean out and culvert replacement work.
- Weather dependent, the Township’s contractor will be lowering manholes on curb and gutter roads on May 22 and 23.
- Weather dependent, the Township’s contractor is scheduled to crush the existing asphalt in place on roads that do NOT have curb and gutter.
- Weather dependent, the Township’s contractor will be milling (i.e. removing existing asphalt) from roads that have curb and gutter on May 29 and 30.
- The milling and crushing work typically moves past a given driveway in approximately 10 minutes, after which there is a rough gravel surface that you can drive on. The milling, crushing and paving work will be completed one lane at a time, thus the streets will be usable on at least one side at almost all times. An entire street is normally milled in one (1) day. Once the milling is finished, the first layer of new asphalt will be placed within 10 days.
- Weather dependent, the Township’s contractor will be paving roads from June 2-6. The roads with curb and gutter are likely to be paved first.
- Additional paving dates will be announced when they are scheduled.
Tacom Hills Update #2
Tacoma Hills Update
Consumers Energy Work
Construction Updates Coming Soon
Questions? We have answers
If you have any questions or concerns about the project, we are here for you. Our project manager is here to answer any of your questions. Feel free to email or call us at any time.